IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

34

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0095 # 01 Y:1987 01 1987 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $84,858 $27,000 Implemented
CO0095 # 02 Y:1987 02 1987 INCREASE AMOUNT OF CONDENSATE RETURNED $19,460 $1,000 Implemented
CO0095 # 09 Y:1987 09 1987 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $581 $0 Not Implemented
CO0095 # 07 Y:1987 07 1987 INSTALL STEAM TRAP $483 $220 Implemented
CO0095 # 03 Y:1987 03 1987 USE COOLING AIR WHICH COOLS HOT WORK PIECES FOR SPACE HEATING $3,467 $500 Not Implemented
CO0095 # 05 Y:1987 05 1987 INSULATE BARE EQUIPMENT $2,502 $950 Not Implemented
CO0095 # 06 Y:1987 06 1987 REPAIR AND ELIMINATE STEAM LEAKS $4,535 $250 Implemented
CO0095 # 04 Y:1987 04 1987 INSTALL / REPAIR INSULATION ON STEAM LINES $573 $500 Implemented
CO0095 # 08 Y:1987 08 1987 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $253 $300 Implemented
CO0089 # 14 Y:1987 14 1987 RECOVER WASTE HEAT FROM EQUIPMENT $1,473 $750 Implemented
CO0090 # 09 Y:1987 09 1987 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $65 $90 Implemented
CO0090 # 08 Y:1987 08 1987 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $1,147 $1,350 Implemented
CO0090 # 06 Y:1987 06 1987 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $375 $500 Implemented
CO0090 # 05 Y:1987 05 1987 AIR CONDITION ONLY SPACE NECESSARY $556 $100 Implemented
CO0090 # 04 Y:1987 04 1987 USE DEMAND CONTROLLER OR LOAD SHEDDER $689 $1,200 Implemented
CO0090 # 03 Y:1987 03 1987 RECOVER WASTE HEAT FROM EQUIPMENT $528 $350 Implemented
CO0089 # 15 Y:1987 15 1987 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $479 $300 Implemented
CO0089 # 13 Y:1987 13 1987 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,437 $1,000 Implemented
CO0089 # 12 Y:1987 12 1987 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $3,066 $750 Implemented
CO0089 # 11 Y:1987 11 1987 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $3,916 $13,440 Not Implemented
CO0089 # 09 Y:1987 09 1987 AIR CONDITION ONLY SPACE NECESSARY $8,911 $2,100 Not Implemented
CO0089 # 08 Y:1987 08 1987 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $19,113 $24,000 Implemented
CO0089 # 06 Y:1987 06 1987 INSTALL TIMERS AND/OR THERMOSTATS $13,198 $0 Implemented
CO0089 # 05 Y:1987 05 1987 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $726 $300 Implemented
CO0089 # 03 Y:1987 03 1987 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $6,537 $500 Implemented