Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,993
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0526 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,660 | $25,050 | Implemented |
GT0526 # 02 Y:1994 | 02 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,810 | $1,340 | Not Implemented |
GT0526 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $42,860 | $189,480 | Not Implemented |
GT0526 # 04 Y:1994 | 04 | 1994 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $51,020 | $135,100 | Not Implemented |
GT0526 # 05 Y:1994 | 05 | 1994 | INSTALL TIMERS AND/OR THERMOSTATS | $10,800 | $13,300 | Not Implemented |
GT0526 # 06 Y:1994 | 06 | 1994 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,120 | $250 | Implemented |
GT0526 # 07 Y:1994 | 07 | 1994 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $189,570 | $279,700 | Not Implemented |
GT0525 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,170 | $32,530 | Implemented |
GT0525 # 05 Y:1994 | 05 | 1994 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $7,600 | $2,550 | Not Implemented |
GT0525 # 06 Y:1994 | 06 | 1994 | COVER OPEN TANKS | $2,280 | $740 | Not Implemented |
GT0525 # 01 Y:1994 | 01 | 1994 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $6,630 | $5,000 | Not Implemented |
GT0525 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,470 | $6,520 | Implemented |
GT0525 # 03 Y:1994 | 03 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,860 | $1,150 | Implemented |
GT0524 # 01 Y:1994 | 01 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,680 | $1,300 | Not Implemented |
GT0524 # 02 Y:1994 | 02 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,160 | $5,030 | Not Implemented |
GT0524 # 03 Y:1994 | 03 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,250 | $8,000 | Not Implemented |
GT0524 # 04 Y:1994 | 04 | 1994 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $2,930 | $5,800 | Not Implemented |
GT0524 # 05 Y:1994 | 05 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,355 | $7,813 | Not Implemented |
GT0524 # 06 Y:1994 | 06 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,707 | $51,104 | Not Implemented |
GT0524 # 07 Y:1994 | 07 | 1994 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,370 | $11,000 | Not Implemented |
GT0520 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,300 | $9,420 | Implemented |
GT0520 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $460 | $835 | Implemented |
GT0520 # 03 Y:1994 | 03 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,900 | $450 | Implemented |
GT0520 # 04 Y:1994 | 04 | 1994 | REPAIR AND ELIMINATE STEAM LEAKS | $3,845 | $500 | Implemented |