Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,660
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0242 # 08 Y:2000 | 08 | 2000 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $4,883 | $123 | Not Implemented |
IA0242 # 09 Y:2000 | 09 | 2000 | APPLY FOR INVESTMENT INCENTIVES | $3,531 | $250 | Not Implemented |
IA0241 # 01 Y:2000 | 01 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,172 | $1,104 | Implemented |
IA0241 # 02 Y:2000 | 02 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $15,055 | $0 | Implemented |
IA0241 # 03 Y:2000 | 03 | 2000 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,987 | $2,000 | Not Implemented |
IA0241 # 04 Y:2000 | 04 | 2000 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $1,474 | $1,474 | Not Implemented |
IA0241 # 05 Y:2000 | 05 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,325 | $39,789 | Implemented |
IA0241 # 06 Y:2000 | 06 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,574 | $0 | Not Implemented |
IA0241 # 07 Y:2000 | 07 | 2000 | INSTALL OCCUPANCY SENSORS | $213 | $466 | Not Implemented |
IA0241 # 08 Y:2000 | 08 | 2000 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $94,641 | $36,700 | Not Implemented |
IA0241 # 09 Y:2000 | 09 | 2000 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $2,750 | $7,900 | Not Implemented |
IA0241 # 10 Y:2000 | 10 | 2000 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $34,515 | $2,950 | Not Implemented |
IA0241 # 11 Y:2000 | 11 | 2000 | COMBINE UTILITY METERS | $5,863 | $100 | Not Implemented |
IA0240 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,330 | $0 | Implemented |
IA0240 # 02 Y:2000 | 02 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,222 | $0 | Implemented |
IA0240 # 03 Y:2000 | 03 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,996 | $463 | Implemented |
IA0240 # 04 Y:2000 | 04 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,204 | $100 | Implemented |
IA0240 # 05 Y:2000 | 05 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,648 | $623 | Implemented |
IA0239 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $59 | $783 | Not Implemented |
IA0239 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $981 | $264 | Implemented |
IA0239 # 04 Y:2000 | 04 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $436 | $130 | Not Implemented |
IA0239 # 05 Y:2000 | 05 | 2000 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $3,777 | $1,142 | Not Implemented |
IA0239 # 06 Y:2000 | 06 | 2000 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $2,140 | $9,600 | Not Implemented |
IA0239 # 07 Y:2000 | 07 | 2000 | USE UTILITY CONTROLLED POWER MANAGEMENT | $7,353 | $125 | Implemented |
IA0239 # 08 Y:2000 | 08 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $187,200 | $234,048 | Not Implemented |