Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,718
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0157 # 01 Y:2003 | 01 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $29,568 | $490 | Not Implemented |
LL0157 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $26,381 | $4,905 | Not Implemented |
LL0157 # 03 Y:2003 | 03 | 2003 | INCREASE AMOUNT OF CONDENSATE RETURNED | $4,189 | $6,875 | Not Implemented |
LL0157 # 04 Y:2003 | 04 | 2003 | OPTIMIZE PLANT POWER FACTOR | $3,129 | $17,080 | Not Implemented |
LL0157 # 05 Y:2003 | 05 | 2003 | USE PHOTOCELL CONTROLS | $1,442 | $756 | Not Implemented |
LL0157 # 06 Y:2003 | 06 | 2003 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $19,617 | $0 | Implemented |
LL0157 # 07 Y:2003 | 07 | 2003 | ELIMINATE/REDUCE AN OPERATION | $4,800 | $0 | Not Implemented |
LL0157 # 08 Y:2003 | 08 | 2003 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $44,506 | $12,900 | Not Implemented |
LL0157 # 09 Y:2003 | 09 | 2003 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $4,938,083 | $100,000 | Not Implemented |
LL0155 # 01 Y:2003 | 01 | 2003 | REPLACE BOILER | $17,740 | $33,000 | Not Implemented |
LL0155 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,929 | $975 | Implemented |
LL0155 # 03 Y:2003 | 03 | 2003 | INSULATE BARE EQUIPMENT | $1,265 | $262 | Implemented |
LL0155 # 04 Y:2003 | 04 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $839 | $75 | Not Implemented |
LL0155 # 05 Y:2003 | 05 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $712 | $756 | Not Implemented |
LL0155 # 06 Y:2003 | 06 | 2003 | INSTALL OCCUPANCY SENSORS | $518 | $364 | Implemented |
LL0155 # 07 Y:2003 | 07 | 2003 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $25,317 | $13,100 | Implemented |
LL0155 # 08 Y:2003 | 08 | 2003 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,006 | $186 | Implemented |
LL0153 # 01 Y:2003 | 01 | 2003 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $380,533 | $1,670,381 | Not Implemented |
LL0153 # 02 Y:2003 | 02 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $161,946 | $1,070 | Implemented |
LL0153 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $33,083 | $12,084 | Implemented |
LL0153 # 04 Y:2003 | 04 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,268 | $983 | Not Implemented |
LL0153 # 05 Y:2003 | 05 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,444 | $0 | Implemented |
LL0153 # 06 Y:2003 | 06 | 2003 | INSTALL OCCUPANCY SENSORS | $2,537 | $0 | Not Implemented |
LL0153 # 07 Y:2003 | 07 | 2003 | USE PHOTOCELL CONTROLS | $1,148 | $494 | Not Implemented |
LL0153 # 08 Y:2003 | 08 | 2003 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $24,960 | $0 | Implemented |