Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
246
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS1222 # 07 Y:2022 | 07 | 2022 | INSTALL OCCUPANCY SENSORS | $243 | $200 | Implemented |
LS1222 # 06 Y:2022 | 06 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $6,500 | $4,700 | Not Implemented |
LS1222 # 05 Y:2022 | 05 | 2022 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $19,500 | $11,480 | Not Implemented |
LS1222 # 04 Y:2022 | 04 | 2022 | USE PHOTOCELL CONTROLS | $3,053 | $222 | Implemented |
LS1222 # 01 Y:2022 | 01 | 2022 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $1,670 | $0 | Implemented |
LS1222 # 02 Y:2022 | 02 | 2022 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $2,620 | $0 | Implemented |
LS1222 # 03 Y:2022 | 03 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $6,112 | $150 | Not Implemented |
LS2218 # 08 Y:2022 | 08 | 2022 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $78,203 | $201,075 | Not Implemented |
LS2218 # 07 Y:2022 | 07 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,287 | $38,480 | Implemented |
LS2218 # 06 Y:2022 | 06 | 2022 | IMPROVE SPACE COMFORT CONDITIONING | $11,310 | $17,640 | Not Implemented |
LS2218 # 05 Y:2022 | 05 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,084 | $800 | Not Implemented |
LS2218 # 04 Y:2022 | 04 | 2022 | ELIMINATE PRACTICE OF MIXING WASTE STREAMS | $12,800 | $2,600 | Not Implemented |
LS2218 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $535 | $90 | Implemented |
LS2218 # 02 Y:2022 | 02 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $3,196 | $100 | Implemented |
LS2218 # 01 Y:2022 | 01 | 2022 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $21,720 | $0 | Implemented |
LS2218 # 09 Y:2022 | 09 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $1,482 | $4,700 | Not Implemented |
LS2218 # 10 Y:2022 | 10 | 2022 | CONVERT TO ROBOTIC PAINTING | $37,576 | $140,000 | Not Implemented |
LS1122 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,233 | $14,801 | Implemented |
LS1122 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $6,168 | $28,864 | Implemented |
LS1122 # 02 Y:2022 | 02 | 2022 | INSTALL OCCUPANCY SENSORS | $73 | $75 | Not Implemented |
LS1122 # 01 Y:2022 | 01 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $5,199 | $175 | Not Implemented |
LS1022 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,360 | $270 | Implemented |
LS1022 # 08 Y:2022 | 08 | 2022 | REPLACE BOILER | $186,054 | $504,000 | Implemented |
LS1022 # 02 Y:2022 | 02 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $1,565 | $88 | Implemented |
LS1022 # 01 Y:2022 | 01 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $1,456 | $0 | Implemented |