Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
87
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0078 # 01 Y:1986 | 01 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,650 | $2,760 | Implemented |
MA0080 # 01 Y:1986 | 01 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,100 | $3,000 | Implemented |
MA0078 # 06 Y:1986 | 06 | 1986 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $14,610 | $22,000 | Implemented |
MA0080 # 02 Y:1986 | 02 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $44,537 | $600 | Implemented |
MA0078 # 05 Y:1986 | 05 | 1986 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $827 | $240 | Implemented |
MA0079 # 03 Y:1986 | 03 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,763 | $4,700 | Implemented |
MA0079 # 02 Y:1986 | 02 | 1986 | REPAIR OR REPLACE STEAM TRAPS | $4,572 | $600 | Implemented |
MA0078 # 03 Y:1986 | 03 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,530 | $3,500 | Implemented |
MA0079 # 01 Y:1986 | 01 | 1986 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $478 | $350 | Implemented |
MA0079 # 05 Y:1986 | 05 | 1986 | USE OPTIMUM THICKNESS INSULATION | $21,098 | $5,000 | Implemented |
MA0076 # 05 Y:1986 | 05 | 1986 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $882 | $3,588 | Implemented |
MA0076 # 01 Y:1986 | 01 | 1986 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $3,524 | $6,000 | Implemented |
MA0075 # 03 Y:1986 | 03 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $565 | $1,136 | Implemented |
MA0076 # 02 Y:1986 | 02 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $526 | $77 | Implemented |
MA0075 # 06 Y:1986 | 06 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $789 | $800 | Implemented |
MA0075 # 07 Y:1986 | 07 | 1986 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,134 | $1,075 | Implemented |
MA0075 # 04 Y:1986 | 04 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,271 | $119 | Implemented |
MA0075 # 08 Y:1986 | 08 | 1986 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,014 | $7,500 | Implemented |
MA0072 # 04 Y:1986 | 04 | 1986 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $9,691 | $720 | Implemented |
MA0074 # 01 Y:1986 | 01 | 1986 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $1,075 | $1,200 | Implemented |
MA0071 # 08 Y:1986 | 08 | 1986 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $3,104 | $6,688 | Implemented |
MA0072 # 05 Y:1986 | 05 | 1986 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $9,992 | $6,740 | Implemented |
MA0072 # 03 Y:1986 | 03 | 1986 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $34,923 | $1,500 | Implemented |
MA0074 # 02 Y:1986 | 02 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $158 | $100 | Implemented |
MA0071 # 03 Y:1986 | 03 | 1986 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $126,986 | $6,650 | Implemented |