IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,692

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MAS025 # 03 Y:2012 03 2012 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $7,097 $0 Not Implemented
MAS025 # 04 Y:2012 04 2012 INSULATE BARE EQUIPMENT $5,622 $935 Not Implemented
MAS025 # 05 Y:2012 05 2012 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT $4,171 $4,300 Implemented
MA0695 # 01 Y:2012 01 2012 BURN A LESS EXPENSIVE GRADE OF FUEL $24,095 $20,000 Not Implemented
MA0695 # 02 Y:2012 02 2012 TURN OFF EQUIPMENT WHEN NOT IN USE $22,626 $5,600 Implemented
MA0695 # 03 Y:2012 03 2012 TURN OFF EQUIPMENT WHEN NOT IN USE $8,891 $200 Implemented
MA0695 # 04 Y:2012 04 2012 UTILIZE A LESS EXPENSIVE COOLING METHOD $6,220 $11,500 Implemented
MA0695 # 05 Y:2012 05 2012 OPTIMIZE PLANT POWER FACTOR $5,965 $10,975 Implemented
MA0695 # 06 Y:2012 06 2012 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $2,830 $1,000 Not Implemented
MA0695 # 07 Y:2012 07 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,676 $1,000 Implemented
MA0695 # 08 Y:2012 08 2012 REDUCE VENTILATION AIR $2,481 $5,375 Not Implemented
MA0695 # 09 Y:2012 09 2012 INSTALL OCCUPANCY SENSORS $2,470 $7,725 Not Implemented
MA0695 # 10 Y:2012 10 2012 INSULATE BARE EQUIPMENT $2,281 $2,630 Not Implemented
MA0695 # 11 Y:2012 11 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,309 $1,260 Implemented
MA0695 # 12 Y:2012 12 2012 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $768 $510 Not Implemented
MAS024 # 01 Y:2012 01 2012 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $19,562 $150 Implemented
MAS024 # 02 Y:2012 02 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,698 $59,484 Not Implemented
MAS024 # 03 Y:2012 03 2012 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $5,802 $22,500 Not Implemented
MAS024 # 04 Y:2012 04 2012 INSULATE BARE EQUIPMENT $4,676 $2,250 Not Implemented
MAS024 # 05 Y:2012 05 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,749 $0 Implemented
MAS024 # 06 Y:2012 06 2012 RECOVER WASTE HEAT FROM EQUIPMENT $1,070 $1,700 Not Implemented
MAS024 # 07 Y:2012 07 2012 INSULATE BARE EQUIPMENT $241 $345 Not Implemented
MA0693 # 01 Y:2012 01 2012 PAY UTILITY BILLS ON TIME $25,247 $500 Implemented
MA0693 # 02 Y:2012 02 2012 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $15,776 $43,000 Not Implemented
MA0693 # 03 Y:2012 03 2012 REPAIR AND ELIMINATE STEAM LEAKS $9,000 $4,200 Implemented