Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,555
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1122 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,248 | $6,134 | Implemented |
OK1122 # 08 Y:2024 | 08 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $575 | $0 | Implemented |
OK1122 # 07 Y:2024 | 07 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $534 | $403 | Implemented |
OK1122 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,929 | $600 | Implemented |
OK1121 # 04 Y:2024 | 04 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $3,722 | $5,451 | Implemented |
OK1120 # 06 Y:2024 | 06 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $865 | $0 | Implemented |
OK1120 # 02 Y:2024 | 02 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,418 | $8,695 | Implemented |
OK1119 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,721 | $17,299 | Implemented |
OK1118 # 04 Y:2024 | 04 | 2024 | OPTIMIZE PLANT POWER FACTOR | $816 | $4,683 | Implemented |
OK1117 # 06 Y:2024 | 06 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $8,042 | $13,524 | Implemented |
OK1117 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,975 | $5,473 | Implemented |
OK1117 # 05 Y:2024 | 05 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $13,497 | $142,202 | Implemented |
OK1117 # 02 Y:2024 | 02 | 2024 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $378 | $178 | Implemented |
OK1117 # 01 Y:2024 | 01 | 2024 | INSTALL OCCUPANCY SENSORS | $196 | $563 | Implemented |
OK1117 # 08 Y:2024 | 08 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $947 | $0 | Implemented |
OK1117 # 07 Y:2024 | 07 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,757 | $7,700 | Implemented |
OK1116 # 01 Y:2024 | 01 | 2024 | OPTIMIZE PLANT POWER FACTOR | $38,052 | $31,569 | Implemented |
OK1116 # 02 Y:2024 | 02 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $17,160 | $7,800 | Implemented |
OK1116 # 05 Y:2024 | 05 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,536 | $0 | Implemented |
OK1114 # 04 Y:2024 | 04 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,371 | $9,240 | Implemented |
OK1114 # 02 Y:2024 | 02 | 2024 | REDUCE VENTILATION AIR | $3,939 | $0 | Implemented |
OK1114 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $223 | $0 | Implemented |
OK1114 # 03 Y:2024 | 03 | 2024 | OPERATE BOILERS ON HIGH FIRE SETTING | $3,357 | $16,000 | Implemented |
OK1113 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $125 | $611 | Implemented |
OK1113 # 01 Y:2024 | 01 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $3,139 | $4,760 | Implemented |