Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

78

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OKO952 # 01 Y:2016 01 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $39,072 $32,000 Implemented
OK0948 # 02 Y:2016 02 2016 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $1,510 $2,320 Implemented
OK0948 # 06 Y:2016 06 2016 REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT $27,228 $83,600 Implemented
OK0948 # 08 Y:2016 08 2016 USE OPTIMUM THICKNESS INSULATION $382 $1,310 Implemented
OK0948 # 09 Y:2016 09 2016 USE OPTIMUM THICKNESS INSULATION $58 $203 Implemented
OK0948 # 11 Y:2016 11 2016 OPTIMIZE PLANT POWER FACTOR $7,251 $25,830 Implemented
OK0946 # 06 Y:2016 06 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,159 $7,320 Implemented
OK0945 # 03 Y:2016 03 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $21,559 $26,380 Implemented
OK0944 # 04 Y:2016 04 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,222 $1,107 Implemented
OK0943 # 01 Y:2016 01 2016 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $40,741 $19,000 Implemented
OK0943 # 02 Y:2016 02 2016 PAY UTILITY BILLS ON TIME $21,826 $0 Implemented
OK0943 # 03 Y:2016 03 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,211 $0 Implemented
OK0943 # 06 Y:2016 06 2016 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $645 $1,405 Implemented
OK0943 # 07 Y:2016 07 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,445 $11,700 Implemented
OK0943 # 08 Y:2016 08 2016 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $5,953 $4,600 Implemented
OK0943 # 09 Y:2016 09 2016 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $1,934 $2,720 Implemented
OK0943 # 10 Y:2016 10 2016 INSTALL SET-BACK TIMERS $1,250 $790 Implemented
OK0943 # 11 Y:2016 11 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,334 $21,372 Implemented
OK0943 # 12 Y:2016 12 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $861 $4,032 Implemented
OK0942 # 03 Y:2016 03 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $972 $4,623 Implemented
OK0942 # 05 Y:2016 05 2016 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $600 $3,450 Implemented
OK0942 # 01 Y:2016 01 2016 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,767 $3,112 Implemented
OK0939 # 06 Y:2016 06 2016 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $3,761 $0 Implemented
OK0939 # 02 Y:2016 02 2016 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $269 $0 Implemented
OK0939 # 01 Y:2016 01 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,199 $1,105 Implemented