Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
195
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
RU0112 # 06 Y:1991 | 06 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,807 | $31,015 | Not Implemented |
RU0103 # 01 Y:1990 | 01 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $664 | $3,750 | Implemented |
RU0103 # 02 Y:1990 | 02 | 1990 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,830 | $0 | Implemented |
RU0103 # 03 Y:1990 | 03 | 1990 | IMPROVE LUBRICATION PRACTICES | $857 | $800 | Not Implemented |
RU0103 # 04 Y:1990 | 04 | 1990 | INSULATE BARE EQUIPMENT | $1,213 | $12,352 | Not Implemented |
RU0103 # 05 Y:1990 | 05 | 1990 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $12,768 | $133,665 | Implemented |
RU0101 # 01 Y:1990 | 01 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $976 | $0 | Implemented |
RU0101 # 02 Y:1990 | 02 | 1990 | COVER OPEN TANKS | $16,298 | $1,468 | Not Implemented |
RU0101 # 03 Y:1990 | 03 | 1990 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $34,441 | $74,800 | Implemented |
RU0101 # 04 Y:1990 | 04 | 1990 | INSTALL STORM WINDOWS AND DOORS | $545 | $750 | Implemented |
RU0080 # 01 Y:1990 | 01 | 1990 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,218 | $68 | Implemented |
RU0080 # 02 Y:1990 | 02 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,495 | $0 | Not Implemented |
RU0080 # 03 Y:1990 | 03 | 1990 | IMPROVE LUBRICATION PRACTICES | $2,478 | $800 | Not Implemented |
RU0080 # 04 Y:1990 | 04 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $602 | $86 | Implemented |
RU0080 # 05 Y:1990 | 05 | 1990 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $6,426 | $3,026 | Not Implemented |
RU0080 # 06 Y:1990 | 06 | 1990 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,454 | $6,245 | Implemented |
RU0080 # 07 Y:1990 | 07 | 1990 | INSTALL SOLID WASTE INCINERATOR FOR HEAT | $123,297 | $1,075,000 | Not Implemented |
RU0081 # 01 Y:1990 | 01 | 1990 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,465 | $350 | Implemented |
RU0081 # 02 Y:1990 | 02 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,110 | $0 | Implemented |
RU0081 # 03 Y:1990 | 03 | 1990 | IMPROVE LUBRICATION PRACTICES | $3,237 | $800 | Not Implemented |
RU0081 # 04 Y:1990 | 04 | 1990 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,558 | $11,400 | Implemented |
RU0081 # 05 Y:1990 | 05 | 1990 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,360 | $3,240 | Not Implemented |
RU0081 # 06 Y:1990 | 06 | 1990 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $4,212 | $0 | Not Implemented |
RU0081 # 07 Y:1990 | 07 | 1990 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $2,160 | $565 | Not Implemented |
RU0064 # 01 Y:1989 | 01 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,083 | $0 | Implemented |