Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
263
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0282 # 13 Y:2001 | 13 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $21,020 | $20,000 | Not Implemented |
SD0282 # 16 Y:2001 | 16 | 2001 | $3,022,214 | $480,000 | Not Implemented | |
SD0282 # 10 Y:2001 | 10 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $348,473 | $150,000 | Not Implemented |
SD0282 # 05 Y:2001 | 05 | 2001 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,312 | $2,000 | Not Implemented |
SD0282 # 02 Y:2001 | 02 | 2001 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,953 | $190 | Implemented |
SD0282 # 12 Y:2001 | 12 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $5,600 | $500 | Not Implemented |
SD0282 # 11 Y:2001 | 11 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $1,832,890 | $1,400,000 | Not Implemented |
SD0282 # 17 Y:2001 | 17 | 2001 | $1,777 | $0 | Implemented | |
SD0282 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $103,026 | $8,000 | Implemented |
SD0282 # 01 Y:2001 | 01 | 2001 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $2,980,189 | $2,980,189 | Not Implemented |
SD0282 # 09 Y:2001 | 09 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,108 | $8,000 | Not Implemented |
SD0282 # 15 Y:2001 | 15 | 2001 | USE EVAPORATION TO CONCENTRATE MATERIAL | $13,681 | $3,000 | Not Implemented |
SD0282 # 07 Y:2001 | 07 | 2001 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $55,555 | $10,000 | Implemented |
SD0282 # 06 Y:2001 | 06 | 2001 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $33,122 | $55,000 | Not Implemented |
SD0282 # 08 Y:2001 | 08 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $83,687 | $110,000 | Not Implemented |
SD0282 # 04 Y:2001 | 04 | 2001 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $6,804 | $3,550 | Implemented |
SD0281 # 03 Y:2001 | 03 | 2001 | INSTALL SKYLIGHTS | $17,602 | $37,000 | Not Implemented |
SD0281 # 02 Y:2001 | 02 | 2001 | UPGRADE OBSOLETE EQUIPMENT | $32,897 | $60,000 | Not Implemented |
SD0281 # 01 Y:2001 | 01 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $34,478 | $1,400 | Implemented |
SD0281 # 06 Y:2001 | 06 | 2001 | UPGRADE OBSOLETE EQUIPMENT | $465,613 | $1,000,000 | Not Implemented |
SD0281 # 05 Y:2001 | 05 | 2001 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $21,557 | $45,000 | Not Implemented |
SD0281 # 07 Y:2001 | 07 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $4,190 | $15,000 | Not Implemented |
SD0281 # 08 Y:2001 | 08 | 2001 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $14,000 | $5,800 | Not Implemented |
SD0281 # 04 Y:2001 | 04 | 2001 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,025 | $2,250 | Not Implemented |
SD0280 # 01 Y:2001 | 01 | 2001 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $38,808 | $51,000 | Not Implemented |