IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

201

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0225 # 02 Y:2001 02 2001 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,216 $112 Implemented
SF0225 # 03 Y:2001 03 2001 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,948 $2,195 Implemented
SF0225 # 07 Y:2001 07 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $230 $618 Not Implemented
SF0224 # 07 Y:2001 07 2001 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $25,962 $13,200 n/a
SF0224 # 02 Y:2001 02 2001 ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS $1,556 $0 n/a
SF0224 # 04 Y:2001 04 2001 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $18,526 $4,994 n/a
SF0224 # 01 Y:2001 01 2001 INSTALL OCCUPANCY SENSORS $9,345 $540 n/a
SF0224 # 05 Y:2001 05 2001 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $10,562 $3,240 n/a
SF0224 # 06 Y:2001 06 2001 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $6,146 $2,800 n/a
SF0224 # 03 Y:2001 03 2001 CLOSE OFF UNNEEDED STEAM LINES $2,618 $172 n/a
SF0224 # 09 Y:2001 09 2001 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $6,142 $6,113 n/a
SF0224 # 08 Y:2001 08 2001 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $11,660 $9,500 n/a
SF0224 # 10 Y:2001 10 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $259,156 $256,500 n/a
SF0224 # 11 Y:2001 11 2001 INSTALL OCCUPANCY SENSORS $17,495 $33,556 n/a
SF0224 # 12 Y:2001 12 2001 OPTIMIZE PLANT POWER FACTOR $120,158 $160,000 n/a
SF0223 # 05 Y:2001 05 2001 INSTALL OCCUPANCY SENSORS $1,304 $1,080 Implemented
SF0223 # 04 Y:2001 04 2001 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $4,914 $2,160 Implemented
SF0223 # 11 Y:2001 11 2001 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $7,473,507 $413,000 Not Implemented
SF0223 # 07 Y:2001 07 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,122 $3,134 Implemented
SF0223 # 13 Y:2001 13 2001 OPTIMIZE PLANT POWER FACTOR $13,899 $20,315 Not Implemented
SF0223 # 06 Y:2001 06 2001 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $885 $900 Implemented
SF0223 # 01 Y:2001 01 2001 TURN OFF EQUIPMENT WHEN NOT IN USE $16,905 $0 Implemented
SF0223 # 02 Y:2001 02 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,094 $0 Not Implemented
SF0223 # 12 Y:2001 12 2001 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $450,000 $50,000 Implemented
SF0223 # 10 Y:2001 10 2001 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,230 $2,999 Not Implemented