Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
220
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0402 # 10 Y:2015 | 10 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $7,911 | $23,244 | Implemented |
SU0402 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $431 | $560 | Implemented |
SU0402 # 11 Y:2015 | 11 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $385 | $1,496 | Not Implemented |
SU0402 # 04 Y:2015 | 04 | 2015 | INSTALL OCCUPANCY SENSORS | $1,500 | $297 | Not Implemented |
SU0402 # 02 Y:2015 | 02 | 2015 | DISCONNECT BALLASTS | $375 | $0 | Not Implemented |
SU0402 # 08 Y:2015 | 08 | 2015 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $1,495 | $2,000 | Implemented |
SU0402 # 06 Y:2015 | 06 | 2015 | ELIMINATE/REDUCE AN OPERATION | $5,835 | $2,320 | Not Implemented |
SU0402 # 01 Y:2015 | 01 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $851 | $0 | Not Implemented |
SU0402 # 07 Y:2015 | 07 | 2015 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $770 | $950 | Implemented |
SU0402 # 03 Y:2015 | 03 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,073 | $600 | Implemented |
SU0402 # 05 Y:2015 | 05 | 2015 | REDUCE VENTILATION AIR | $8,182 | $2,941 | Implemented |
SU0401 # 01 Y:2015 | 01 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,820 | $0 | Implemented |
SU0401 # 06 Y:2015 | 06 | 2015 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $218 | $404 | Not Implemented |
SU0401 # 07 Y:2015 | 07 | 2015 | ELIMINATE/REDUCE AN OPERATION | $956 | $3,709 | Not Implemented |
SU0401 # 03 Y:2015 | 03 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $964 | $469 | Not Implemented |
SU0401 # 05 Y:2015 | 05 | 2015 | REPLACE BOILER | $11,805 | $10,686 | Implemented |
SU0401 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $383 | $240 | Implemented |
SU0401 # 08 Y:2015 | 08 | 2015 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $9,780 | $49,000 | Not Implemented |
SU0401 # 02 Y:2015 | 02 | 2015 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $3,274 | $1,580 | Implemented |
SU0400 # 03 Y:2015 | 03 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $325 | $0 | Implemented |
SU0400 # 10 Y:2015 | 10 | 2015 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,639 | $5,931 | Implemented |
SU0400 # 08 Y:2015 | 08 | 2015 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $5,273 | $6,721 | Implemented |
SU0400 # 09 Y:2015 | 09 | 2015 | INSTALL OCCUPANCY SENSORS | $517 | $709 | Not Implemented |
SU0400 # 01 Y:2015 | 01 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,287 | $0 | Not Implemented |
SU0400 # 02 Y:2015 | 02 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $4,921 | $0 | Not Implemented |