Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
147
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TA0019 # 05 Y:2001 | 05 | 2001 | INSTALL OCCUPANCY SENSORS | $1,015 | $346 | Implemented |
TA0019 # 04 Y:2001 | 04 | 2001 | USE EVAPORATION TO CONCENTRATE MATERIAL | $5,184 | $5,331 | Implemented |
TA0019 # 02 Y:2001 | 02 | 2001 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $11,836 | $225 | Implemented |
TA0019 # 06 Y:2001 | 06 | 2001 | INSTALL / REPAIR INSULATION ON STEAM LINES | $161 | $140 | Not Implemented |
TA0019 # 03 Y:2001 | 03 | 2001 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $5,994 | $3,000 | Not Implemented |
TA0019 # 01 Y:2001 | 01 | 2001 | $27,478 | $2,805 | Not Implemented | |
TA0020 # 06 Y:2001 | 06 | 2001 | INSULATE BARE EQUIPMENT | $685 | $140 | Implemented |
TA0020 # 05 Y:2001 | 05 | 2001 | INSULATE BARE EQUIPMENT | $1,110 | $321 | Implemented |
TA0020 # 07 Y:2001 | 07 | 2001 | INSTALL OCCUPANCY SENSORS | $584 | $320 | Implemented |
TA0020 # 03 Y:2001 | 03 | 2001 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $3,260 | $240 | Implemented |
TA0020 # 04 Y:2001 | 04 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,415 | $1,715 | Implemented |
TA0020 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,175 | $26,460 | n/a |
TA0020 # 02 Y:2001 | 02 | 2001 | $4,751 | $0 | Implemented | |
TA0020 # 08 Y:2001 | 08 | 2001 | INSULATE BARE EQUIPMENT | $370 | $160 | Implemented |
TA0016 # 09 Y:2001 | 09 | 2001 | INSTALL OCCUPANCY SENSORS | $1,032 | $320 | Implemented |
TA0016 # 10 Y:2001 | 10 | 2001 | DISCONNECT BALLASTS | $510 | $982 | Not Implemented |
TA0016 # 02 Y:2001 | 02 | 2001 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $15,055 | $600 | Implemented |
TA0016 # 11 Y:2001 | 11 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $254 | $542 | Implemented |
TA0016 # 03 Y:2001 | 03 | 2001 | INSULATE BARE EQUIPMENT | $13,585 | $2,910 | Implemented |
TA0016 # 08 Y:2001 | 08 | 2001 | USE SYNTHETIC LUBRICANT | $1,600 | $0 | Not Implemented |
TA0016 # 04 Y:2001 | 04 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,090 | $1,200 | Implemented |
TA0016 # 01 Y:2001 | 01 | 2001 | REPLACE BOILER | $420,482 | $9,456 | Implemented |
TA0016 # 07 Y:2001 | 07 | 2001 | USE PHOTOCELL CONTROLS | $1,696 | $225 | Implemented |
TA0016 # 06 Y:2001 | 06 | 2001 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,920 | $54 | Implemented |
TA0016 # 05 Y:2001 | 05 | 2001 | COVER OPEN TANKS | $2,000 | $3,900 | Not Implemented |