Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,950
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0286 # 02 Y:1986 | 02 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $2,353 | $1,315 | Not Implemented |
TN0286 # 03 Y:1986 | 03 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,478 | $0 | Implemented |
TN0286 # 04 Y:1986 | 04 | 1986 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,097 | $3,500 | Implemented |
TN0286 # 05 Y:1986 | 05 | 1986 | HEAT WATER WITH EXHAUST HEAT | $875 | $3,900 | Not Implemented |
TN0286 # 06 Y:1986 | 06 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,285 | $615 | Implemented |
TN0286 # 07 Y:1986 | 07 | 1986 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $744 | $300 | Implemented |
TN0287 # 01 Y:1986 | 01 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,791 | $0 | Not Implemented |
TN0287 # 02 Y:1986 | 02 | 1986 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $5,418 | $17,075 | Not Implemented |
TN0287 # 03 Y:1986 | 03 | 1986 | INSULATE BARE EQUIPMENT | $1,458 | $398 | Not Implemented |
TN0287 # 04 Y:1986 | 04 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,277 | $750 | Implemented |
TN0287 # 05 Y:1986 | 05 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,422 | $820 | Not Implemented |
TN0287 # 06 Y:1986 | 06 | 1986 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $288 | $1,000 | Implemented |
TN0287 # 07 Y:1986 | 07 | 1986 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $159 | $35 | Implemented |
TN0287 # 08 Y:1986 | 08 | 1986 | INSTALL SET-BACK TIMERS | $531 | $0 | Not Implemented |
TN0287 # 09 Y:1986 | 09 | 1986 | USE MINIMUM STEAM OPERATING PRESSURE | $82 | $0 | Implemented |
TN0288 # 01 Y:1986 | 01 | 1986 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $4,032 | $8,712 | Not Implemented |
TN0288 # 02 Y:1986 | 02 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,648 | $0 | Not Implemented |
TN0288 # 03 Y:1986 | 03 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $881 | $120 | Implemented |
TN0288 # 04 Y:1986 | 04 | 1986 | INSTALL SET-BACK TIMERS | $534 | $0 | Implemented |
TN0288 # 05 Y:1986 | 05 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $537 | $236 | Implemented |
TN0288 # 06 Y:1986 | 06 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $223 | $600 | Implemented |
TN0289 # 01 Y:1986 | 01 | 1986 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $64,485 | $105,000 | Not Implemented |
TN0289 # 02 Y:1986 | 02 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $32,373 | $4,500 | Implemented |
TN0289 # 03 Y:1986 | 03 | 1986 | REPAIR AND ELIMINATE STEAM LEAKS | $11,562 | $150 | Implemented |
TN0289 # 04 Y:1986 | 04 | 1986 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $143,750 | $40,000 | Implemented |