Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,211
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL2502 # 01 Y:2025 | 01 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,810 | $2,205 | n/a |
UL2502 # 04 Y:2025 | 04 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $94 | $35 | n/a |
UL2502 # 08 Y:2025 | 08 | 2025 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $8,276 | $1,800 | n/a |
UL2502 # 06 Y:2025 | 06 | 2025 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,639 | $0 | n/a |
UL2502 # 03 Y:2025 | 03 | 2025 | OPTIMIZE PLANT POWER FACTOR | $2,331 | $7,280 | n/a |
UL2502 # 05 Y:2025 | 05 | 2025 | INSTALL OCCUPANCY SENSORS | $753 | $155 | n/a |
UL2502 # 02 Y:2025 | 02 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,066 | $0 | n/a |
UL2502 # 07 Y:2025 | 07 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $74,556 | $570,771 | n/a |
UL2501 # 06 Y:2025 | 06 | 2025 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $141,151 | $58,367 | n/a |
UL2501 # 03 Y:2025 | 03 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,347 | $574 | n/a |
UL2501 # 04 Y:2025 | 04 | 2025 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $592 | $0 | n/a |
UL2501 # 01 Y:2025 | 01 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,472 | $0 | n/a |
UL2501 # 07 Y:2025 | 07 | 2025 | OPTIMIZE PLANT POWER FACTOR | $25,794 | $14,820 | n/a |
UL2501 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,462 | $1,440 | n/a |
UL2501 # 09 Y:2025 | 09 | 2025 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $38,672 | $8,000 | n/a |
UL2501 # 08 Y:2025 | 08 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $95,468 | $929,060 | n/a |
UL2501 # 05 Y:2025 | 05 | 2025 | INSTALL OCCUPANCY SENSORS | $1,240 | $2,661 | n/a |
UL2419 # 03 Y:2024 | 03 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,384 | $7,500 | n/a |
UL2419 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,526 | $2,160 | n/a |
UL2419 # 06 Y:2024 | 06 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $79,016 | $599,215 | n/a |
UL2419 # 04 Y:2024 | 04 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,825 | $8,450 | n/a |
UL2419 # 05 Y:2024 | 05 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $434 | $2,275 | n/a |
UL2419 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $411 | $0 | n/a |
UL2418 # 02 Y:2024 | 02 | 2024 | INSULATE BARE EQUIPMENT | $160 | $1,155 | n/a |
UL2418 # 01 Y:2024 | 01 | 2024 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $5,142 | $6,500 | n/a |