Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
92
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0248 # 05 Y:2024 | 05 | 2024 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $6,380 | $133,800 | n/a |
UU0248 # 04 Y:2024 | 04 | 2024 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $33,420 | $319,250 | n/a |
UU0248 # 03 Y:2024 | 03 | 2024 | USE AUTOMATIC FLOW CONTROL | $820 | $4,250 | n/a |
UU0248 # 07 Y:2024 | 07 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,570 | $9,360 | n/a |
UU0248 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,740 | $1,270 | n/a |
UU0248 # 01 Y:2024 | 01 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $980 | $2,600 | n/a |
UU0248 # 06 Y:2024 | 06 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $940 | $3,000 | n/a |
UU0247 # 03 Y:2024 | 03 | 2024 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $200,000 | $717,040 | n/a |
UU0247 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $864 | $7,540 | n/a |
UU0247 # 01 Y:2024 | 01 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,970 | $3,000 | n/a |
UU0247 # 02 Y:2024 | 02 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,770 | $9,500 | n/a |
UU0247 # 04 Y:2024 | 04 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $1,060 | $1,950 | n/a |
UU0235 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,664 | $1,013 | n/a |
UU0235 # 03 Y:2024 | 03 | 2024 | INSULATE BARE EQUIPMENT | $12,478 | $23,282 | n/a |
UU0235 # 04 Y:2024 | 04 | 2024 | USE OPTIMUM THICKNESS INSULATION | $6,968 | $8,826 | n/a |
UU0235 # 02 Y:2024 | 02 | 2024 | USE STEAM SPARGING OR INJECTIONS IN PLACE OF INDIRECT HEATING | $271,861 | $3,050,000 | n/a |
UU0236 # 02 Y:2024 | 02 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $72,320 | $46,000 | n/a |
UU0236 # 01 Y:2024 | 01 | 2024 | REPLACE BOILER | $208,300 | $1,070,720 | n/a |
UU0236 # 04 Y:2024 | 04 | 2024 | INSULATE BARE EQUIPMENT | $5,640 | $3,090 | n/a |
UU0236 # 03 Y:2024 | 03 | 2024 | INSULATE BARE EQUIPMENT | $16,698 | $11,570 | n/a |
UU0225 # 01 Y:2023 | 01 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $39,842 | $126,388 | Implemented |
UU0225 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,874 | $0 | Implemented |
UU0225 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,399 | $15,200 | Implemented |
UU0225 # 05 Y:2023 | 05 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,851 | $2,775 | Implemented |