IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,298

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0385 # 02 Y:2000 02 2000 MODIFY STORAGE SPACE TO AVOID RENTAL OF A WAREHOUSE $23,175 $15,487 Implemented
WI0385 # 03 Y:2000 03 2000 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS $15,000 $10,000 Implemented
WI0385 # 04 Y:2000 04 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $7,415 $0 Not Implemented
WI0385 # 05 Y:2000 05 2000 INSTALL TIMERS AND/OR THERMOSTATS $5,954 $1,200 Not Implemented
WI0385 # 06 Y:2000 06 2000 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS $3,665 $1,000 Not Implemented
WI0385 # 07 Y:2000 07 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,895 $60 Implemented
WI0385 # 08 Y:2000 08 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $404 $740 Not Implemented
WI0385 # 09 Y:2000 09 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,819 $6,986 Not Implemented
WI0385 # 10 Y:2000 10 2000 RECOVER WASTE HEAT FROM EQUIPMENT $459 $2,000 Not Implemented
WI0385 # 11 Y:2000 11 2000 REDUCE VENTILATION AIR $436 $1,000 Not Implemented
WI0385 # 12 Y:2000 12 2000 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $167 $245 Not Implemented
WI0384 # 01 Y:2000 01 2000 INSTALL SENSORS TO DETECT DEFECTS $141,912 $70,000 Not Implemented
WI0384 # 02 Y:2000 02 2000 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $18,107 $20,000 Not Implemented
WI0384 # 03 Y:2000 03 2000 RECOVER WASTE HEAT FROM EQUIPMENT $17,119 $6,500 Not Implemented
WI0384 # 04 Y:2000 04 2000 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $9,935 $3,250 Not Implemented
WI0384 # 05 Y:2000 05 2000 INSTALL TIMERS AND/OR THERMOSTATS $5,952 $1,000 Not Implemented
WI0384 # 06 Y:2000 06 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,745 $640 Not Implemented
WI0384 # 07 Y:2000 07 2000 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $1,623 $1,033 Not Implemented
WI0384 # 08 Y:2000 08 2000 INSULATE BARE EQUIPMENT $1,185 $427 Not Implemented
WI0384 # 09 Y:2000 09 2000 USE OPTIMUM THICKNESS INSULATION $370 $375 Not Implemented
WI0383 # 01 Y:2000 01 2000 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $41,291 $72,000 Not Implemented
WI0383 # 02 Y:2000 02 2000 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $14,801 $20,000 Not Implemented
WI0383 # 03 Y:2000 03 2000 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $7,946 $22,500 Implemented
WI0383 # 04 Y:2000 04 2000 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $4,492 $11,550 Implemented
WI0383 # 05 Y:2000 05 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $3,875 $0 Not Implemented