IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

73,780

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
KU0193 # 02 Y:1986 02 1986 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $769 $100 Implemented
KU0193 # 03 Y:1986 03 1986 INSTALL TIMERS AND/OR THERMOSTATS $4,524 $667 Implemented
KU0193 # 05 Y:1986 05 1986 INSTALL AUTOMATIC STACK DAMPER $1,097 $500 Implemented
KU0193 # 08 Y:1986 08 1986 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $111 $0 Implemented
KU0194 # 01 Y:1986 01 1986 ADD AIR SHIELDS TO TRUCKS TO INCREASE FUEL MILEAGE $1,687 $0 Implemented
KU0194 # 02 Y:1986 02 1986 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,003 $1,575 Implemented
KU0194 # 03 Y:1986 03 1986 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $393 $50 Implemented
KU0195 # 02 Y:1986 02 1986 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $3,374 $14 Implemented
KU0195 # 04 Y:1986 04 1986 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,705 $0 Implemented
KU0195 # 05 Y:1986 05 1986 INSTALL TIMERS AND/OR THERMOSTATS $4,203 $106 Implemented
KU0195 # 06 Y:1986 06 1986 INSTALL SET-BACK TIMERS $1,360 $222 Implemented
KU0195 # 07 Y:1986 07 1986 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $964 $600 Implemented
KU0195 # 08 Y:1986 08 1986 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $148 $200 Implemented
KU0195 # 09 Y:1986 09 1986 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $124 $200 Implemented
KU0195 # 10 Y:1986 10 1986 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $229 $0 Implemented
KU0195 # 11 Y:1986 11 1986 INSTALL AUTOMATIC STACK DAMPER $456 $700 Implemented
KU0195 # 12 Y:1986 12 1986 IMPROVE LUBRICATION PRACTICES $495 $200 Implemented
KU0195 # 13 Y:1986 13 1986 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $272 $0 Implemented
LT0053 # 01 Y:1986 01 1986 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $3,910 $0 Implemented
LT0053 # 02 Y:1986 02 1986 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $575 $0 Implemented
LT0053 # 05 Y:1986 05 1986 REPAIR AND ELIMINATE STEAM LEAKS $2,214 $2,000 Implemented
LT0053 # 08 Y:1986 08 1986 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $408 $1,000 Implemented
LT0055 # 01 Y:1986 01 1986 INSULATE BARE EQUIPMENT $287 $270 Implemented
LT0055 # 03 Y:1986 03 1986 USE OPTIMUM THICKNESS INSULATION $4,130 $5,659 Implemented
LT0055 # 06 Y:1986 06 1986 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,847 $16,480 Implemented