Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,891
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0217 # 02 Y:1987 | 02 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,326 | $2,808 | Implemented |
OK0217 # 03 Y:1987 | 03 | 1987 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $2,969 | $9,033 | Implemented |
OK0217 # 04 Y:1987 | 04 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,396 | $1,000 | Implemented |
KU0210 # 01 Y:1986 | 01 | 1986 | IMPROVE LUBRICATION PRACTICES | $7,588 | $3,325 | Implemented |
KU0210 # 02 Y:1986 | 02 | 1986 | INSTALL SET-BACK TIMERS | $5,599 | $2,100 | Implemented |
KU0210 # 03 Y:1986 | 03 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,772 | $0 | Implemented |
KU0210 # 04 Y:1986 | 04 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $876 | $0 | Implemented |
KU0210 # 07 Y:1986 | 07 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $693 | $50 | Implemented |
KU0210 # 08 Y:1986 | 08 | 1986 | RECOVER WASTE HEAT FROM EQUIPMENT | $371 | $200 | Implemented |
KU0207 # 02 Y:1986 | 02 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $18,525 | $0 | Implemented |
KU0207 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,480 | $0 | Implemented |
KU0207 # 04 Y:1986 | 04 | 1986 | INSTALL SET-BACK TIMERS | $9,165 | $1,494 | Implemented |
KU0207 # 06 Y:1986 | 06 | 1986 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $5,637 | $6,030 | Implemented |
KU0207 # 07 Y:1986 | 07 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $2,817 | $52 | Implemented |
KU0207 # 09 Y:1986 | 09 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,433 | $0 | Implemented |
KU0207 # 11 Y:1986 | 11 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $547 | $0 | Implemented |
KU0207 # 12 Y:1986 | 12 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $516 | $150 | Implemented |
KU0207 # 13 Y:1986 | 13 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $469 | $0 | Implemented |
KU0207 # 14 Y:1986 | 14 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $454 | $20 | Implemented |
KU0207 # 16 Y:1986 | 16 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $128 | $100 | Implemented |
KU0207 # 17 Y:1986 | 17 | 1986 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $160 | $300 | Implemented |
KU0208 # 02 Y:1986 | 02 | 1986 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $4,084 | $100 | Implemented |
KU0208 # 04 Y:1986 | 04 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $295 | $0 | Implemented |
KU0208 # 05 Y:1986 | 05 | 1986 | INSTALL AUTOMATIC STACK DAMPER | $655 | $200 | Implemented |
KU0208 # 06 Y:1986 | 06 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $217 | $0 | Implemented |