IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,681

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MI0247 # 06 Y:2013 06 2013 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $2,908 $2,520 Implemented
MI0247 # 08 Y:2013 08 2013 MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT $870 $347 Implemented
MI0246 # 01 Y:2013 01 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $30,416 $2,300 Implemented
MI0246 # 02 Y:2013 02 2013 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $14,747 $17,000 Implemented
MI0246 # 03 Y:2013 03 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,442 $1,660 Implemented
MI0246 # 07 Y:2013 07 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,508 $4,420 Implemented
MI0246 # 08 Y:2013 08 2013 PAY BILLS ON TIME TO AVOID LATE FEES $945 $240 Implemented
MI0246 # 09 Y:2013 09 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $876 $80 Implemented
MI0245 # 01 Y:2013 01 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $30,611 $1,800 Implemented
MI0245 # 03 Y:2013 03 2013 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $24,698 $160 Implemented
MI0245 # 04 Y:2013 04 2013 INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE $13,325 $13,200 Implemented
MI0245 # 05 Y:2013 05 2013 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $12,407 $1,680 Implemented
MI0245 # 06 Y:2013 06 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,737 $1,660 Implemented
MI0245 # 07 Y:2013 07 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,337 $80 Implemented
MI0245 # 08 Y:2013 08 2013 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $2,960 $7,502 Implemented
MI0245 # 11 Y:2013 11 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,631 $3,190 Implemented
MI0245 # 12 Y:2013 12 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $1,214 $1,694 Implemented
MI0244 # 02 Y:2013 02 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $4,361 $1,800 Implemented
MI0244 # 03 Y:2013 03 2013 INSTALL SKYLIGHTS $3,415 $2,780 Implemented
MI0244 # 05 Y:2013 05 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,214 $80 Implemented
MI0244 # 07 Y:2013 07 2013 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $2,411 $80 Implemented
MI0244 # 09 Y:2013 09 2013 INSTALL OCCUPANCY SENSORS $2,117 $446 Implemented
MI0244 # 10 Y:2013 10 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,192 $1,660 Implemented
MI0243 # 01 Y:2013 01 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $24,158 $2,300 Implemented
MI0243 # 02 Y:2013 02 2013 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $13,601 $80 Implemented