Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75,198
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0366 # 04 Y:2024 | 04 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $11,668 | $59,968 | Implemented |
SD0661 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,348 | $676 | Implemented |
SD0661 # 05 Y:2024 | 05 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $10,205 | $0 | Implemented |
SD0661 # 06 Y:2024 | 06 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,354 | $0 | Implemented |
SD0661 # 07 Y:2024 | 07 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $854 | $250 | Implemented |
SD0661 # 09 Y:2024 | 09 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,243 | $7,340 | Implemented |
SD0661 # 11 Y:2024 | 11 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $970 | $1,863 | Implemented |
SD0661 # 13 Y:2024 | 13 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,043 | $19,842 | Implemented |
SD0661 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $1,321,862 | $54,390 | Implemented |
SD0661 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $641,754 | $589,764 | Implemented |
LS1024 # 01 Y:2024 | 01 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,372 | $0 | Implemented |
LS1024 # 02 Y:2024 | 02 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $343 | $0 | Implemented |
LS1024 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,551 | $5,440 | Implemented |
IC0313 # 01 Y:2024 | 01 | 2024 | OPTIMIZE OPERATION OF MULTI-STAGE VACUUM STEAM JETS | $9,651 | $7,079 | Implemented |
IC0313 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,562 | $0 | Implemented |
IC0313 # 06 Y:2024 | 06 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,557 | $0 | Implemented |
IC0313 # 09 Y:2024 | 09 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $19,590 | $704 | Implemented |
IC0313 # 10 Y:2024 | 10 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,979 | $2,430 | Implemented |
IC0313 # 11 Y:2024 | 11 | 2024 | INSULATE BARE EQUIPMENT | $4,631 | $8,869 | Implemented |
LS0924 # 01 Y:2024 | 01 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,991 | $0 | Implemented |
LS0924 # 02 Y:2024 | 02 | 2024 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $1,667 | $250 | Implemented |
LS0924 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,495 | $10,257 | Implemented |
LS0924 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $27,561 | $98,980 | Implemented |
UD1093 # 05 Y:2024 | 05 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,522 | $2,450 | Implemented |
UD1093 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,442 | $953 | Implemented |