Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,050
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0149 # 01 Y:1984 | 01 | 1984 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $34,443 | $3,262 | Implemented |
KU0148 # 01 Y:1984 | 01 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,910 | $36 | Implemented |
KU0148 # 14 Y:1984 | 14 | 1984 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $760 | $0 | Implemented |
KU0149 # 02 Y:1984 | 02 | 1984 | INSULATE BARE EQUIPMENT | $3,920 | $350 | Implemented |
CO0015 # 04 Y:1984 | 04 | 1984 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $694 | $1,127 | Implemented |
GT0237 # 02 Y:1984 | 02 | 1984 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $574 | $970 | Implemented |
KU0148 # 05 Y:1984 | 05 | 1984 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $366 | $100 | Implemented |
CO0015 # 03 Y:1984 | 03 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $290 | $50 | Implemented |
CO0014 # 01 Y:1984 | 01 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,292 | $300 | Implemented |
KU0148 # 02 Y:1984 | 02 | 1984 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $2,754 | $3,000 | Implemented |
KU0148 # 03 Y:1984 | 03 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $514 | $800 | Implemented |
CO0015 # 10 Y:1984 | 10 | 1984 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,676 | $5,000 | Implemented |
CO0014 # 02 Y:1984 | 02 | 1984 | INSTALL / REPAIR INSULATION ON STEAM LINES | $561 | $300 | Implemented |
CO0014 # 05 Y:1984 | 05 | 1984 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $4,970 | $1,000 | Implemented |
KU0148 # 09 Y:1984 | 09 | 1984 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $298 | $12 | Implemented |
GT0237 # 03 Y:1984 | 03 | 1984 | REPAIR AND ELIMINATE STEAM LEAKS | $1,730 | $100 | Implemented |
CO0014 # 03 Y:1984 | 03 | 1984 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $74 | $135 | Implemented |
KU0148 # 10 Y:1984 | 10 | 1984 | REDUCE VENTILATION AIR | $2,954 | $500 | Implemented |
CO0015 # 11 Y:1984 | 11 | 1984 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $335 | $250 | Implemented |
CO0015 # 06 Y:1984 | 06 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $791 | $230 | Implemented |
CO0015 # 02 Y:1984 | 02 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $300 | $300 | Implemented |
KU0148 # 04 Y:1984 | 04 | 1984 | INSTALL AUTOMATIC STACK DAMPER | $436 | $700 | Implemented |
CO0015 # 01 Y:1984 | 01 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $963 | $908 | Implemented |
KU0148 # 13 Y:1984 | 13 | 1984 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,182 | $2,000 | Implemented |
UD0147 # 05 Y:1984 | 05 | 1984 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $588 | $680 | Implemented |