Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,874
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2317 # 11 Y:2023 | 11 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $321,413 | $2,701,940 | Not Implemented |
UC2317 # 12 Y:2023 | 12 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $5,411 | $0 | Not Implemented |
AS0567 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $100,430 | $774,239 | Implemented |
AS0567 # 02 Y:2023 | 02 | 2023 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $86,125 | $165,996 | Not Implemented |
AS0567 # 03 Y:2023 | 03 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $57,803 | $10,720 | Not Implemented |
AS0567 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,255 | $31,926 | Not Implemented |
AS0567 # 05 Y:2023 | 05 | 2023 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $647 | $384 | Not Implemented |
UL2316 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $14,992 | $0 | n/a |
UL2316 # 02 Y:2023 | 02 | 2023 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $73,247 | $137,300 | n/a |
UL2316 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $112,167 | $989,084 | n/a |
UL2316 # 04 Y:2023 | 04 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,026 | $0 | n/a |
UL2316 # 05 Y:2023 | 05 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $15,036 | $20,000 | n/a |
UL2316 # 06 Y:2023 | 06 | 2023 | INSTALL HYDROGEN FUEL CELL | $281,388 | $1,750,000 | n/a |
MZ0355 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $60,563 | $285,000 | Not Implemented |
MZ0355 # 02 Y:2023 | 02 | 2023 | LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION | $9,825 | $7,940 | Not Implemented |
MZ0355 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $860 | $750 | Not Implemented |
MZ0355 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $17,125 | $42,980 | Not Implemented |
MZ0355 # 05 Y:2023 | 05 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $15,922 | $78,200 | Not Implemented |
MZ0355 # 06 Y:2023 | 06 | 2023 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $29,986 | $2,880 | Not Implemented |
MZ0355 # 07 Y:2023 | 07 | 2023 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $1,043 | $320 | Implemented |
KS2324 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $63,860 | $598,739 | n/a |
KS2324 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,738 | $5,480 | n/a |
KS2324 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $32,201 | $0 | n/a |
KS2324 # 04 Y:2023 | 04 | 2023 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $12,787 | $8,320 | n/a |
KS2324 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,344 | $22,467 | n/a |