Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,636
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0019 # 02 Y:1995 | 02 | 1995 | OPTIMIZE PLANT POWER FACTOR | $5,174 | $3,750 | Implemented |
MS0019 # 03 Y:1995 | 03 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,539 | $500 | Implemented |
MS0019 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,429 | $1,436 | Implemented |
MS0019 # 05 Y:1995 | 05 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,563 | $0 | Not Implemented |
MS0019 # 06 Y:1995 | 06 | 1995 | INSTALL / REPAIR INSULATION ON STEAM LINES | $675 | $1,540 | Not Implemented |
MS0019 # 07 Y:1995 | 07 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $633 | $1,800 | Implemented |
MS0018 # 01 Y:1995 | 01 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,304 | $3,500 | Not Implemented |
MS0018 # 02 Y:1995 | 02 | 1995 | OPTIMIZE PLANT POWER FACTOR | $2,506 | $4,500 | Not Implemented |
MS0018 # 03 Y:1995 | 03 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,296 | $7,800 | Implemented |
MS0018 # 04 Y:1995 | 04 | 1995 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $954 | $2,500 | Not Implemented |
MS0018 # 05 Y:1995 | 05 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $727 | $1,000 | Not Implemented |
MS0018 # 06 Y:1995 | 06 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $503 | $254 | Implemented |
MS0018 # 07 Y:1995 | 07 | 1995 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,193 | $1,000 | Implemented |
MS0017 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,234 | $355 | Implemented |
MS0017 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $207 | $97 | Implemented |
MS0017 # 03 Y:1995 | 03 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,284 | $3,000 | Not Implemented |
MS0017 # 04 Y:1995 | 04 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $882 | $1,700 | Not Implemented |
MS0017 # 05 Y:1995 | 05 | 1995 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,076 | $15,000 | Not Implemented |
MS0017 # 06 Y:1995 | 06 | 1995 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,784 | $1,000 | Implemented |
MS0016 # 01 Y:1995 | 01 | 1995 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $2,800 | $3,000 | Not Implemented |
MS0016 # 02 Y:1995 | 02 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,568 | $3,000 | Not Implemented |
MS0016 # 03 Y:1995 | 03 | 1995 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,498 | $2,500 | Implemented |
MS0016 # 04 Y:1995 | 04 | 1995 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $526 | $1,000 | Not Implemented |
MS0016 # 05 Y:1995 | 05 | 1995 | USE PHOTOCELL CONTROLS | $300 | $150 | Not Implemented |
MS0015 # 01 Y:1994 | 01 | 1994 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,248 | $0 | Implemented |