Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,871
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0235 # 03 Y:1984 | 03 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $10,346 | $0 | Implemented |
TN0235 # 04 Y:1984 | 04 | 1984 | INSTALL / REPAIR INSULATION ON STEAM LINES | $13,854 | $1,011 | Implemented |
TN0235 # 05 Y:1984 | 05 | 1984 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $16,218 | $2,000 | Implemented |
TN0235 # 06 Y:1984 | 06 | 1984 | COVER OPEN TANKS | $4,463 | $300 | Implemented |
TN0235 # 07 Y:1984 | 07 | 1984 | INCREASE AMOUNT OF CONDENSATE RETURNED | $3,149 | $3,230 | Not Implemented |
TN0235 # 08 Y:1984 | 08 | 1984 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,383 | $106 | Not Implemented |
TN0235 # 09 Y:1984 | 09 | 1984 | INSTALL SET-BACK TIMERS | $3,408 | $0 | Implemented |
TN0235 # 10 Y:1984 | 10 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $258 | $60 | Implemented |
TN0221 # 01 Y:1984 | 01 | 1984 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $4,406 | $7,000 | Not Implemented |
TN0221 # 02 Y:1984 | 02 | 1984 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,248 | $8,600 | Not Implemented |
TN0221 # 03 Y:1984 | 03 | 1984 | INSTALL SET-BACK TIMERS | $2,849 | $10,000 | Not Implemented |
TN0221 # 04 Y:1984 | 04 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $773 | $475 | Implemented |
TN0221 # 05 Y:1984 | 05 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $967 | $0 | Implemented |
TN0221 # 06 Y:1984 | 06 | 1984 | INSTALL AUTOMATIC STACK DAMPER | $148 | $420 | Implemented |
TN0221 # 07 Y:1984 | 07 | 1984 | USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD | $237 | $0 | Implemented |
TN0222 # 01 Y:1984 | 01 | 1984 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $171,149 | $240,000 | Not Implemented |
TN0222 # 02 Y:1984 | 02 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,367 | $0 | Implemented |
TN0222 # 03 Y:1984 | 03 | 1984 | INSULATE BARE EQUIPMENT | $1,224 | $1,817 | Implemented |
TN0222 # 04 Y:1984 | 04 | 1984 | USE MINIMUM STEAM OPERATING PRESSURE | $687 | $0 | Not Implemented |
TN0222 # 05 Y:1984 | 05 | 1984 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $14,520 | $3,000 | Implemented |
TN0222 # 06 Y:1984 | 06 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $953 | $270 | Implemented |