Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,533
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0398 # 03 Y:2005 | 03 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,293 | $2,902 | Not Implemented |
AS0398 # 04 Y:2005 | 04 | 2005 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $811 | $0 | Not Implemented |
AS0398 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,184 | $4,984 | Not Implemented |
AS0398 # 06 Y:2005 | 06 | 2005 | INSTALL SENSORS TO DETECT AND AVOID JAMS | $251,744 | $8,000 | Not Implemented |
TA0094 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,225 | $410 | Implemented |
TA0094 # 02 Y:2005 | 02 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,585 | $125 | Implemented |
TA0094 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,640 | $0 | Not Implemented |
TA0094 # 04 Y:2005 | 04 | 2005 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $325 | $0 | Not Implemented |
TA0094 # 05 Y:2005 | 05 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $175 | $0 | Not Implemented |
UD0718 # 01 Y:2005 | 01 | 2005 | USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | $409,000 | $15,000 | Not Implemented |
UD0718 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $77,400 | $62,900 | Not Implemented |
UD0718 # 03 Y:2005 | 03 | 2005 | USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | $64,584 | $200,000 | Implemented |
UD0718 # 04 Y:2005 | 04 | 2005 | INSULATE BARE EQUIPMENT | $42,615 | $44,322 | Not Implemented |
UD0718 # 05 Y:2005 | 05 | 2005 | DEVELOP A REPAIR/REPLACE POLICY | $45,734 | $178,576 | Not Implemented |
UD0718 # 06 Y:2005 | 06 | 2005 | REDUCE VENTILATION AIR | $37,367 | $19,721 | Not Implemented |
UD0718 # 07 Y:2005 | 07 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,025 | $13,430 | Not Implemented |
UD0718 # 08 Y:2005 | 08 | 2005 | USE PHOTOCELL CONTROLS | $4,300 | $12,500 | Not Implemented |
UD0718 # 09 Y:2005 | 09 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,805 | $2,598 | Not Implemented |
UD0718 # 10 Y:2005 | 10 | 2005 | USE POWER DURING OFF-PEAK PERIODS | $2,913 | $0 | Not Implemented |
UD0718 # 11 Y:2005 | 11 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,522 | $3,044 | Implemented |
UD0718 # 12 Y:2005 | 12 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $762 | $362 | Not Implemented |
SF0304 # 01 Y:2005 | 01 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $17,326 | $0 | Not Implemented |
SF0304 # 02 Y:2005 | 02 | 2005 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $871 | $0 | Not Implemented |
SF0304 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,751 | $0 | Implemented |
SF0304 # 04 Y:2005 | 04 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,623 | $0 | Not Implemented |