Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,644
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0260 # 09 Y:2007 | 09 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $234 | $500 | Not Implemented |
LE0260 # 10 Y:2007 | 10 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,501 | $54,052 | Not Implemented |
LE0258 # 05 Y:2007 | 05 | 2007 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $767 | $150 | Not Implemented |
LE0258 # 06 Y:2007 | 06 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,367 | $40,684 | Not Implemented |
LE0258 # 07 Y:2007 | 07 | 2007 | INSTALL OCCUPANCY SENSORS | $387 | $1,400 | Not Implemented |
LE0258 # 01 Y:2007 | 01 | 2007 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $13,092 | $6,400 | Not Implemented |
LE0258 # 02 Y:2007 | 02 | 2007 | USE RADIANT HEATER FOR SPOT HEATING | $12,411 | $18,750 | Not Implemented |
LE0258 # 03 Y:2007 | 03 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,871 | $10,000 | Not Implemented |
LE0258 # 04 Y:2007 | 04 | 2007 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $6,874 | $5,000 | Not Implemented |
LE0257 # 01 Y:2007 | 01 | 2007 | USE OPTIMUM TEMPERATURE | $14,693 | $3,500 | Implemented |
LE0257 # 02 Y:2007 | 02 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13,241 | $10,000 | Not Implemented |
LE0257 # 03 Y:2007 | 03 | 2007 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,861 | $6,000 | Not Implemented |
LE0257 # 04 Y:2007 | 04 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,031 | $0 | Implemented |
LE0257 # 05 Y:2007 | 05 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $661 | $800 | Not Implemented |
LE0257 # 06 Y:2007 | 06 | 2007 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $641 | $2,000 | Not Implemented |
LE0257 # 07 Y:2007 | 07 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,008 | $5,752 | Not Implemented |
LE0257 # 08 Y:2007 | 08 | 2007 | INSTALL OCCUPANCY SENSORS | $1,047 | $150 | Implemented |
DL0003 # 01 Y:2007 | 01 | 2007 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $14,287 | $45,000 | Not Implemented |
DL0003 # 02 Y:2007 | 02 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $47,542 | $92,679 | Not Implemented |
DL0003 # 03 Y:2007 | 03 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $25,891 | $2,000 | Not Implemented |
DL0003 # 04 Y:2007 | 04 | 2007 | USE MINIMUM STEAM OPERATING PRESSURE | $1,497 | $0 | Implemented |
DL0003 # 05 Y:2007 | 05 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $24,500 | $10,000 | Not Implemented |
DL0003 # 06 Y:2007 | 06 | 2007 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $51,975 | $25,000 | Not Implemented |
DL0003 # 07 Y:2007 | 07 | 2007 | INSTALL / REPAIR INSULATION ON STEAM LINES | $23,137 | $20,000 | Implemented |
DL0003 # 08 Y:2007 | 08 | 2007 | REPLACE BOILER | $4,572 | $15,400 | Not Implemented |