IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,821

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1090 # 03 Y:2023 03 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,602 $1,797 Implemented
OK1090 # 04 Y:2023 04 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,316 $3,638 Implemented
OK1090 # 05 Y:2023 05 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $68,844 $438,000 Not Implemented
CI0015 # 01 Y:2023 01 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $88,567 $1,500 Not Implemented
CI0015 # 02 Y:2023 02 2023 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $36,511 $165,000 Implemented
CI0015 # 03 Y:2023 03 2023 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $11,757 $0 Not Implemented
CI0015 # 04 Y:2023 04 2023 REPLACE BOILER $3,770 $9,000 Not Implemented
CI0015 # 05 Y:2023 05 2023 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $1,958 $3,500 Not Implemented
CI0015 # 06 Y:2023 06 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,444 $2,700 Not Implemented
CI0015 # 07 Y:2023 07 2023 RECOVER WASTE HEAT FROM EQUIPMENT $1,292 $5,000 Not Implemented
CI0015 # 08 Y:2023 08 2023 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,262 $1,310 Not Implemented
MUWT01 # 01 Y:2023 01 2023 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $70 $0 Not Implemented
MUWT01 # 02 Y:2023 02 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $539 $2,176 Not Implemented
MUWT01 # 03 Y:2023 03 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $206 $960 Not Implemented
MUWT01 # 04 Y:2023 04 2023 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $715 $0 Implemented
MUWT01 # 05 Y:2023 05 2023 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS $120 $0 Implemented
MUWT01 # 06 Y:2023 06 2023 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $126,128 $453,578 Not Implemented
SU0530 # 01 Y:2023 01 2023 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $3,551 $211 Not Implemented
SU0530 # 02 Y:2023 02 2023 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,608 $1,343 Not Implemented
SU0530 # 03 Y:2023 03 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $283 $402 Not Implemented
SU0530 # 04 Y:2023 04 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,441 $6,444 Not Implemented
SU0530 # 05 Y:2023 05 2023 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $2,131 $8,940 Not Implemented
SU0530 # 06 Y:2023 06 2023 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $3,193 $21,150 Not Implemented
SU0530 # 07 Y:2023 07 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $4,126 $28,596 Not Implemented
SF0601 # 01 Y:2023 01 2023 TURN OFF EQUIPMENT WHEN NOT IN USE $35,057 $0 Implemented