Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,602
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0584 # 03 Y:2010 | 03 | 2010 | USE SYNTHETIC LUBRICANT | $10,225 | $0 | Not Implemented |
AM0584 # 04 Y:2010 | 04 | 2010 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,880 | $0 | Not Implemented |
AM0584 # 05 Y:2010 | 05 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,115 | $6,560 | Not Implemented |
AM0584 # 06 Y:2010 | 06 | 2010 | PAY UTILITY BILLS ON TIME | $1,680 | $0 | Implemented |
AM0584 # 07 Y:2010 | 07 | 2010 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $880 | $135 | Implemented |
AM0584 # 08 Y:2010 | 08 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $610 | $100 | Implemented |
AM0583 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,970 | $26,490 | Implemented |
AM0583 # 02 Y:2010 | 02 | 2010 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,360 | $0 | Implemented |
AM0583 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,447 | $680 | Implemented |
AM0583 # 04 Y:2010 | 04 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,120 | $500 | Implemented |
AM0583 # 05 Y:2010 | 05 | 2010 | PAY UTILITY BILLS ON TIME | $479 | $0 | Implemented |
AM0583 # 06 Y:2010 | 06 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $210 | $10 | Implemented |
AM0583 # 07 Y:2010 | 07 | 2010 | USE SYNTHETIC LUBRICANT | $130 | $0 | Implemented |
AM0582 # 01 Y:2010 | 01 | 2010 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $404,300 | $3,000 | Implemented |
AM0582 # 02 Y:2010 | 02 | 2010 | TURN OFF EQUIPMENT WHEN NOT IN USE | $147,000 | $5,600 | Implemented |
AM0582 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $116,300 | $220,000 | Implemented |
AM0582 # 04 Y:2010 | 04 | 2010 | Hire Energy Manager | $97,900 | $0 | Not Implemented |
AM0582 # 05 Y:2010 | 05 | 2010 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $64,500 | $50,000 | Not Implemented |
AM0582 # 06 Y:2010 | 06 | 2010 | INSTALL SUB-METERING EQUIPMENT | $48,000 | $5,000 | Implemented |
AM0582 # 07 Y:2010 | 07 | 2010 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $33,670 | $2,400 | Not Implemented |
AM0582 # 08 Y:2010 | 08 | 2010 | OPTIMIZE PLANT POWER FACTOR | $27,950 | $0 | Not Implemented |
AM0582 # 09 Y:2010 | 09 | 2010 | INSTALL SKYLIGHTS | $15,400 | $14,200 | Not Implemented |
AM0582 # 10 Y:2010 | 10 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,400 | $2,000 | Implemented |
AM0582 # 11 Y:2010 | 11 | 2010 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,120 | $430 | Not Implemented |
AM0582 # 12 Y:2010 | 12 | 2010 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,540 | $130 | Implemented |