IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,304

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WV0418 # 12 Y:2010 12 2010 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $9,456 $5,095 Implemented
WV0418 # 13 Y:2010 13 2010 RECOVER WASTE HEAT FROM EQUIPMENT $6,837 $3,870 Not Implemented
WV0418 # 14 Y:2010 14 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,456 $621 Implemented
WV0418 # 15 Y:2010 15 2010 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $5,931 $0 Implemented
WV0418 # 16 Y:2010 16 2010 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES $4,116 $0 Implemented
WV0418 # 17 Y:2010 17 2010 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $866 $2,717 Implemented
WV0418 # 18 Y:2010 18 2010 IMPROVE LUBRICATION PRACTICES $370 $466 Implemented
UM0377 # 01 Y:2010 01 2010 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $4,826 $600,000 Not Implemented
UM0377 # 02 Y:2010 02 2010 UPGRADE CONTROLS ON COMPRESSORS $4,594 $7,127 Not Implemented
UM0377 # 03 Y:2010 03 2010 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $421 $200 Not Implemented
UM0377 # 04 Y:2010 04 2010 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $71 $10 Not Implemented
UM0377 # 05 Y:2010 05 2010 USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) $47,701 $4,568 Not Implemented
UM0377 # 06 Y:2010 06 2010 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $11,037 $8,500 Not Implemented
UM0377 # 07 Y:2010 07 2010 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $14,767 $700 Not Implemented
UM0377 # 08 Y:2010 08 2010 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $2,554 $11,607 Not Implemented
UM0377 # 09 Y:2010 09 2010 REPROCESS SPENT OILS ON SITE FOR RE-USE $626 $627 Not Implemented
DL0063 # 01 Y:2010 01 2010 TURN OFF EQUIPMENT WHEN NOT IN USE $35,600 $100 Implemented
DL0063 # 02 Y:2010 02 2010 REDUCE VENTILATION AIR $34,080 $500 Implemented
DL0063 # 03 Y:2010 03 2010 INCREASE AMOUNT OF CONDENSATE RETURNED $31,600 $1,610 Implemented
DL0063 # 04 Y:2010 04 2010 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $33,400 $57,000 Not Implemented
DL0063 # 05 Y:2010 05 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $31,900 $166,850 Implemented
DL0063 # 06 Y:2010 06 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $22,000 $3,000 Implemented
DL0063 # 07 Y:2010 07 2010 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $18,958 $60,000 Not Implemented
DL0063 # 08 Y:2010 08 2010 TURN OFF EQUIPMENT WHEN NOT IN USE $12,220 $100 Not Implemented
DL0063 # 09 Y:2010 09 2010 REDUCE EXCESS STEAM BLEEDING $14,034 $419 Implemented