Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,703
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0456 # 06 Y:2014 | 06 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,511 | $18,537 | Implemented |
TT0142 # 01 Y:2014 | 01 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,305 | $1,400 | Implemented |
TT0142 # 02 Y:2014 | 02 | 2014 | INSTALL / REPAIR INSULATION ON STEAM LINES | $299 | $596 | Not Implemented |
TT0142 # 03 Y:2014 | 03 | 2014 | INSTALL / REPAIR INSULATION ON STEAM LINES | $861 | $1,662 | Not Implemented |
TT0142 # 04 Y:2014 | 04 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,651 | $3,000 | Implemented |
TT0142 # 05 Y:2014 | 05 | 2014 | DISCONNECT BALLASTS | $555 | $60 | Not Implemented |
TT0142 # 06 Y:2014 | 06 | 2014 | USE PHOTOCELL CONTROLS | $49 | $45 | Implemented |
TT0146 # 01 Y:2014 | 01 | 2014 | REPAIR AND ELIMINATE STEAM LEAKS | $1,943 | $822 | Implemented |
TT0146 # 02 Y:2014 | 02 | 2014 | INSTALL SKYLIGHTS | $2,012 | $14,000 | Not Implemented |
TT0146 # 03 Y:2014 | 03 | 2014 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $1,898 | $24,450 | Not Implemented |
TT0146 # 04 Y:2014 | 04 | 2014 | BURN WASTE PAPER FOR HEAT | $5,426 | $19,895 | Not Implemented |
CO0698 # 01 Y:2014 | 01 | 2014 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,950 | $300 | Not Implemented |
CO0698 # 02 Y:2014 | 02 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,570 | $500 | Implemented |
CO0698 # 03 Y:2014 | 03 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,800 | $16,900 | Implemented |
CO0698 # 04 Y:2014 | 04 | 2014 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $6,000 | $1,500 | Not Implemented |
NC0530 # 01 Y:2014 | 01 | 2014 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $14,069 | $54,000 | Not Implemented |
NC0530 # 02 Y:2014 | 02 | 2014 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $1,055 | $0 | Implemented |
NC0530 # 03 Y:2014 | 03 | 2014 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,962 | $200 | Implemented |
NC0530 # 04 Y:2014 | 04 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,946 | $18,000 | Not Implemented |
NC0530 # 05 Y:2014 | 05 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,542 | $5,000 | Not Implemented |
NC0530 # 06 Y:2014 | 06 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $443 | $200 | Implemented |
NC0530 # 07 Y:2014 | 07 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,767 | $4,000 | Not Implemented |
NC0530 # 08 Y:2014 | 08 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,623 | $2,350 | Implemented |
NC0530 # 09 Y:2014 | 09 | 2014 | INSTALL OCCUPANCY SENSORS | $2,127 | $6,420 | Not Implemented |
NC0530 # 10 Y:2014 | 10 | 2014 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $686 | $563 | Implemented |