Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,443
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NL0032 # 02 Y:2019 | 02 | 2019 | USE ULTRASONIC CLEANING | $13,380 | $15,575 | Implemented |
NL0032 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $126 | $500 | Implemented |
NL0031 # 01 Y:2019 | 01 | 2019 | USE OPTIMUM TEMPERATURE | $1,023,132 | $178,000 | Implemented |
NL0031 # 02 Y:2019 | 02 | 2019 | INSTALL TURBULATORS | $66,132 | $93,000 | Implemented |
NL0031 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,344 | $46,600 | Implemented |
NL0031 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,390 | $24,394 | Implemented |
NL0031 # 05 Y:2019 | 05 | 2019 | REPAIR AND ELIMINATE STEAM LEAKS | $5,225 | $1,600 | Not Implemented |
NL0029 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,632 | $18,300 | Implemented |
NL0029 # 02 Y:2019 | 02 | 2019 | USE SAND FOR OTHER PURPOSES (EG CONSTRUCTION FILL, COVER FOR MUNICIPAL LANDFILLS) | $11,970 | $4,500 | Not Implemented |
NL0029 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $393 | $1,500 | Implemented |
NL0028 # 01 Y:2019 | 01 | 2019 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $23,879 | $45,000 | Not Implemented |
NL0028 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,950 | $52,450 | Implemented |
NL0028 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $3,028 | $4,631 | Implemented |
NL0028 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,582 | $1,600 | Implemented |
NL0028 # 05 Y:2019 | 05 | 2019 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $132 | $474 | Not Implemented |
NL0027 # 01 Y:2018 | 01 | 2018 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $24,797 | $32,620 | Implemented |
NL0027 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,840 | $74,980 | Implemented |
NL0027 # 03 Y:2018 | 03 | 2018 | INSULATE BARE EQUIPMENT | $4,500 | $2,500 | Not Implemented |
NL0027 # 04 Y:2018 | 04 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $607 | $1,050 | Not Implemented |
NL0027 # 05 Y:2018 | 05 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $326 | $1,000 | Implemented |
NL0026 # 01 Y:2018 | 01 | 2018 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $28,240 | $65,000 | Not Implemented |
NL0026 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,570 | $69,390 | Implemented |
NL0026 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $450 | $1,000 | Implemented |
NL0026 # 04 Y:2018 | 04 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $450 | $0 | Not Implemented |
NL0025 # 01 Y:2018 | 01 | 2018 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $7,194 | $15,000 | Not Implemented |