Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,130
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0481 # 02 Y:1993 | 02 | 1993 | INSTALL SPECTRAL REFLECTORS / DELAMP | $12,347 | $13,957 | Not Implemented |
TN0481 # 03 Y:1993 | 03 | 1993 | IMPROVE COMBUSTION CONTROL CAPABILITY | $459 | $625 | Implemented |
TN0481 # 04 Y:1993 | 04 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,512 | $510 | Implemented |
TN0481 # 05 Y:1993 | 05 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,178 | $741 | Implemented |
HO0038 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,165 | $1,505 | Implemented |
HO0038 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,023 | $2,742 | Implemented |
HO0038 # 03 Y:1993 | 03 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $583 | $1,300 | Not Implemented |
HO0038 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $674 | $1,000 | Implemented |
HO0039 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,561 | $1,262 | Not Implemented |
HO0039 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $284 | $674 | Not Implemented |
HO0039 # 03 Y:1993 | 03 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $53 | $200 | Not Implemented |
HO0039 # 04 Y:1993 | 04 | 1993 | INSTALL / REPAIR INSULATION ON STEAM LINES | $28 | $99 | Not Implemented |
HO0039 # 05 Y:1993 | 05 | 1993 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,224 | $4,000 | Not Implemented |
HO0039 # 06 Y:1993 | 06 | 1993 | INSTALL OCCUPANCY SENSORS | $608 | $400 | Not Implemented |
WI0172 # 01 Y:1993 | 01 | 1993 | CONSIDER THREE OR FOUR DAYS AROUND-THE-CLOCK OPERATION RATHER THAN ONE OR TWO SHIFTS PER DAY | $12,563 | $0 | Not Implemented |
WI0172 # 02 Y:1993 | 02 | 1993 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,625 | $6,300 | Not Implemented |
WI0172 # 03 Y:1993 | 03 | 1993 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,318 | $2,904 | Not Implemented |
WI0172 # 04 Y:1993 | 04 | 1993 | INSTALL STORM WINDOWS AND DOORS | $318 | $337 | Not Implemented |
WI0172 # 05 Y:1993 | 05 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $928 | $3,473 | Implemented |
WI0172 # 06 Y:1993 | 06 | 1993 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,105 | $1,800 | Implemented |
WI0172 # 07 Y:1993 | 07 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $249 | $0 | Not Implemented |
WI0172 # 08 Y:1993 | 08 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $132 | $640 | Implemented |
WI0173 # 01 Y:1993 | 01 | 1993 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,690 | $400 | Implemented |
WI0173 # 02 Y:1993 | 02 | 1993 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $69 | $0 | Not Implemented |
WI0173 # 03 Y:1993 | 03 | 1993 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,943 | $0 | Implemented |