Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
12,007
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0435 # 01 Y:2011 | 01 | 2011 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $704 | $0 | Implemented |
SD0435 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,875 | $700 | Implemented |
SD0435 # 03 Y:2011 | 03 | 2011 | USE DIRECT FLAME IMPINGEMENT OR INFRARED PROCESSING FOR CHAMBER TYPE HEATING | $14,990 | $3,784 | Not Implemented |
SD0435 # 04 Y:2011 | 04 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,988 | $4,310 | Implemented |
SD0435 # 05 Y:2011 | 05 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,282 | $1,000 | Implemented |
SD0435 # 06 Y:2011 | 06 | 2011 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $866 | $840 | Implemented |
SD0434 # 01 Y:2011 | 01 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $799 | $100 | Implemented |
SD0434 # 02 Y:2011 | 02 | 2011 | INSTALL OCCUPANCY SENSORS | $7,897 | $1,387 | Implemented |
SD0434 # 03 Y:2011 | 03 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,711 | $500 | Not Implemented |
SD0434 # 04 Y:2011 | 04 | 2011 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $4,279 | $4,751 | Not Implemented |
SD0434 # 05 Y:2011 | 05 | 2011 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $1,400 | $2,063 | Implemented |
SD0434 # 06 Y:2011 | 06 | 2011 | INSTALL SKYLIGHTS | $11,302 | $26,616 | Not Implemented |
SF0397 # 01 Y:2011 | 01 | 2011 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $12,161 | $0 | Implemented |
SF0397 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,394 | $0 | Implemented |
SF0397 # 03 Y:2011 | 03 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,482 | $1,759 | Not Implemented |
SF0397 # 04 Y:2011 | 04 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $12,301 | $9,456 | Not Implemented |
SF0397 # 05 Y:2011 | 05 | 2011 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,066 | $2,420 | Implemented |
SF0397 # 06 Y:2011 | 06 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,920 | $6,639 | Not Implemented |
SF0397 # 07 Y:2011 | 07 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,428 | $6,271 | Implemented |
SF0397 # 08 Y:2011 | 08 | 2011 | INSTALL OCCUPANCY SENSORS | $3,294 | $7,163 | Implemented |
SF0397 # 09 Y:2011 | 09 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $19,656 | $79,881 | Implemented |
SF0397 # 10 Y:2011 | 10 | 2011 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $28,839 | $152,713 | Not Implemented |
SF0396 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,923 | $0 | Implemented |
SF0396 # 02 Y:2011 | 02 | 2011 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,498 | $1,199 | Implemented |
SF0396 # 03 Y:2011 | 03 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,230 | $1,731 | Not Implemented |