Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,403
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0090 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $348 | $577 | Implemented |
SF0090 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,366 | $13,620 | Implemented |
SF0090 # 03 Y:1996 | 03 | 1996 | INSULATE BARE EQUIPMENT | $8,425 | $3,900 | Implemented |
SF0090 # 04 Y:1996 | 04 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $833 | $0 | Implemented |
SF0090 # 05 Y:1996 | 05 | 1996 | USE SYNTHETIC LUBRICANT | $434 | $525 | Implemented |
SF0090 # 06 Y:1996 | 06 | 1996 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $2,880 | $500 | Implemented |
SF0090 # 07 Y:1996 | 07 | 1996 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $981 | $0 | Implemented |
ME0191 # 01 Y:1996 | 01 | 1996 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $4,148 | $4,800 | Not Implemented |
ME0191 # 02 Y:1996 | 02 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,679 | $600 | Implemented |
ME0191 # 03 Y:1996 | 03 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,670 | $1,070 | Implemented |
ME0191 # 04 Y:1996 | 04 | 1996 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,594 | $1,530 | Implemented |
ME0191 # 05 Y:1996 | 05 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $1,984 | $2,400 | Implemented |
ME0191 # 06 Y:1996 | 06 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,191 | $4,542 | Implemented |
ME0191 # 07 Y:1996 | 07 | 1996 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $848 | $200 | Implemented |
ME0191 # 08 Y:1996 | 08 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $783 | $1,200 | Implemented |
ME0191 # 09 Y:1996 | 09 | 1996 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $782 | $10,247 | Implemented |
MO0174 # 01 Y:1996 | 01 | 1996 | USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES | $3,746 | $0 | Implemented |
MO0174 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,941 | $12,048 | Implemented |
MO0174 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,374 | $1,439 | Implemented |
MO0174 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $336 | $0 | Implemented |
MO0174 # 05 Y:1996 | 05 | 1996 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,245 | $90 | Not Implemented |
MO0174 # 06 Y:1996 | 06 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,143 | $271 | Implemented |
MO0174 # 07 Y:1996 | 07 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $79 | $0 | Implemented |
AS0175 # 01 Y:1996 | 01 | 1996 | UPGRADE CONTROLS ON COMPRESSORS | $3,647 | $11,000 | Not Implemented |
AS0175 # 02 Y:1996 | 02 | 1996 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,105 | $6,800 | Not Implemented |