IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,703

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0135 # 06 Y:2014 06 2014 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $7,480 $0 Not Implemented
DL0135 # 07 Y:2014 07 2014 TURN OFF EQUIPMENT WHEN NOT IN USE $3,400 $0 Implemented
DL0135 # 08 Y:2014 08 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $10,230 $0 Not Implemented
DL0135 # 09 Y:2014 09 2014 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,170 $270 Not Implemented
DL0135 # 10 Y:2014 10 2014 REDUCE VENTILATION AIR $5,610 $5,900 Not Implemented
BS0046 # 01 Y:2014 01 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $26,312 $58,240 Implemented
BS0046 # 02 Y:2014 02 2014 INSTALL OCCUPANCY SENSORS $3,053 $30 Implemented
BS0046 # 03 Y:2014 03 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $876 $2,756 Implemented
BS0046 # 04 Y:2014 04 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,860 $9,526 Not Implemented
BS0046 # 05 Y:2014 05 2014 INSTALL OCCUPANCY SENSORS $338 $300 Not Implemented
BS0046 # 06 Y:2014 06 2014 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $8,235 $752 Implemented
BS0046 # 07 Y:2014 07 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $401 $922 Implemented
BS0046 # 08 Y:2014 08 2014 REPAIR OR REPLACE STEAM TRAPS $25,901 $50,324 Implemented
BS0046 # 09 Y:2014 09 2014 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $9,395 $84 Implemented
BS0046 # 10 Y:2014 10 2014 INSTALL / REPAIR INSULATION ON STEAM LINES $91 $341 Implemented
BS0046 # 11 Y:2014 11 2014 INSULATE BARE EQUIPMENT $581 $1,533 Not Implemented
BS0046 # 12 Y:2014 12 2014 INSULATE BARE EQUIPMENT $723 $3,015 Not Implemented
BS0046 # 13 Y:2014 13 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $23,944 $70,000 Implemented
IP0029 # 01 Y:2014 01 2014 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $9,363 $210 Not Implemented
IP0029 # 02 Y:2014 02 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,383 $92 Not Implemented
IP0029 # 03 Y:2014 03 2014 INSTALL OCCUPANCY SENSORS $980 $122 Not Implemented
IP0029 # 04 Y:2014 04 2014 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $82,707 $12,435 Not Implemented
IP0029 # 05 Y:2014 05 2014 INSULATE BARE EQUIPMENT $2,997 $1,104 Not Implemented
IP0029 # 06 Y:2014 06 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,419 $512 Not Implemented
IP0029 # 07 Y:2014 07 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,432 $4,014 Implemented