Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,533
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0396 # 05 Y:2005 | 05 | 2005 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $912 | $1,000 | Not Implemented |
AS0396 # 06 Y:2005 | 06 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,302 | $1,000 | Not Implemented |
AS0396 # 07 Y:2005 | 07 | 2005 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $8,063 | $3,000 | Not Implemented |
WI0487 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,912 | $11,200 | Implemented |
WI0487 # 02 Y:2005 | 02 | 2005 | INSTALL SPECTRAL REFLECTORS / DELAMP | $933 | $0 | Implemented |
WI0487 # 03 Y:2005 | 03 | 2005 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $5,262 | $5,600 | Implemented |
WI0487 # 04 Y:2005 | 04 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,836 | $780 | Implemented |
WI0487 # 05 Y:2005 | 05 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $714 | $1,280 | Implemented |
WI0487 # 06 Y:2005 | 06 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $334 | $400 | Implemented |
WI0487 # 07 Y:2005 | 07 | 2005 | INSTALL TIMERS AND/OR THERMOSTATS | $1,350 | $1,200 | Implemented |
WI0487 # 08 Y:2005 | 08 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,185 | $1,400 | Not Implemented |
WI0487 # 09 Y:2005 | 09 | 2005 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,172 | $0 | Implemented |
WI0487 # 10 Y:2005 | 10 | 2005 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,165 | $3,000 | Not Implemented |
WI0487 # 11 Y:2005 | 11 | 2005 | COVER OPEN TANKS | $1,108 | $360 | Not Implemented |
UD0713 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $84,867 | $94,373 | Not Implemented |
UD0713 # 02 Y:2005 | 02 | 2005 | USE OPTIMUM TEMPERATURE | $64,754 | $2,500 | Not Implemented |
UD0713 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,435 | $41,783 | Implemented |
UD0713 # 04 Y:2005 | 04 | 2005 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $15,628 | $3,900 | Not Implemented |
UD0713 # 05 Y:2005 | 05 | 2005 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,868 | $22,600 | Not Implemented |
UD0713 # 06 Y:2005 | 06 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,925 | $200 | Implemented |
UD0713 # 07 Y:2005 | 07 | 2005 | DEVELOP A REPAIR/REPLACE POLICY | $1,021 | $3,807 | Implemented |
OK0703 # 01 Y:2005 | 01 | 2005 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $37,468 | $34,300 | Not Implemented |
OK0703 # 02 Y:2005 | 02 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,044 | $25,020 | Implemented |
OK0703 # 03 Y:2005 | 03 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $36,596 | $39,180 | Implemented |
OK0703 # 04 Y:2005 | 04 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $53,659 | $1,739 | Not Implemented |