Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,880
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CM1017 # 04 Y:2023 | 04 | 2023 | REPLACE BOILER | $20,045 | $41,481 | Implemented |
CM1017 # 05 Y:2023 | 05 | 2023 | USE DOUBLE OR TRIPLE GLAZED WINDOWS TO MAINTAIN HIGHER RELATIVE HUMIDITY AND TO REDUCE HEAT LOSSES | $1,538 | $4,396 | Implemented |
CM1017 # 06 Y:2023 | 06 | 2023 | INSTALL SYSTEM TO COLLECT SCRAP | $9,880 | $2,306 | Not Implemented |
CM1017 # 07 Y:2023 | 07 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $1,464 | $3,500 | Implemented |
IP0170 # 01 Y:2023 | 01 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,367 | $0 | Not Implemented |
IP0170 # 02 Y:2023 | 02 | 2023 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $1,771 | $0 | Not Implemented |
IP0170 # 03 Y:2023 | 03 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $14,876 | $495 | Not Implemented |
IP0170 # 04 Y:2023 | 04 | 2023 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $6,289 | $660 | Not Implemented |
IP0170 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,696 | $4,266 | Not Implemented |
IP0170 # 06 Y:2023 | 06 | 2023 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $590 | $113 | Not Implemented |
IP0170 # 07 Y:2023 | 07 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $140 | $33 | Not Implemented |
IP0170 # 08 Y:2023 | 08 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,620 | $564 | Not Implemented |
IP0170 # 09 Y:2023 | 09 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,123 | $6,636 | Not Implemented |
IP0170 # 10 Y:2023 | 10 | 2023 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $195 | $600 | Not Implemented |
AM0876 # 01 Y:2023 | 01 | 2023 | USE SYNTHETIC LUBRICANT | $1,823 | $0 | Not Implemented |
AM0876 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,373 | $63 | Implemented |
AM0876 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $25,280 | $4,875 | Not Implemented |
AM0876 # 04 Y:2023 | 04 | 2023 | OPTIMIZE PLANT POWER FACTOR | $20,029 | $25,217 | Implemented |
MS0411 # 01 Y:2023 | 01 | 2023 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $16,956 | $42,807 | n/a |
MS0411 # 02 Y:2023 | 02 | 2023 | INSTALL OCCUPANCY SENSORS | $113 | $335 | n/a |
MS0411 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $56,198 | $786,625 | n/a |
MS0411 # 04 Y:2023 | 04 | 2023 | COVER CONTAINERS TO MINIMIZE EVAPORATIVE LOSSES | $4,180 | $4,512 | n/a |
MS0411 # 05 Y:2023 | 05 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $537 | $3,690 | n/a |
MA0855 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $63,886 | $285,949 | n/a |
MA0855 # 02 Y:2023 | 02 | 2023 | USE HEAT PUMP FOR SPACE CONDITIONING | $3,299 | $22,900 | n/a |