IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,043

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0425 # 03 Y:2013 03 2013 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $4,974 $5,906 Not Implemented
SF0425 # 04 Y:2013 04 2013 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $1,255 $2,240 Not Implemented
SF0425 # 05 Y:2013 05 2013 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $30,904 $9,885 Not Implemented
SF0425 # 06 Y:2013 06 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,808 $7,235 Implemented
SF0425 # 07 Y:2013 07 2013 INSTALL OCCUPANCY SENSORS $3,416 $13,849 Implemented
SF0425 # 08 Y:2013 08 2013 HEAT WATER DURING OFF-PEAK PERIODS AND STORE FOR LATER USE $692 $2,830 Implemented
OK0839 # 01 Y:2013 01 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,514 $27,500 Implemented
OK0839 # 02 Y:2013 02 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,540 $0 Implemented
OK0839 # 03 Y:2013 03 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,395 $1,750 Implemented
OK0839 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,494 $33,218 Implemented
OK0839 # 05 Y:2013 05 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $506 $3,114 Not Implemented
OK0839 # 06 Y:2013 06 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $667 $3,677 Not Implemented
OK0839 # 07 Y:2013 07 2013 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $2,708 $5,684 Implemented
OK0839 # 08 Y:2013 08 2013 INSTALL SET-BACK TIMERS $921 $1,630 Not Implemented
OK0839 # 09 Y:2013 09 2013 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $873 $490 Implemented
OK0839 # 10 Y:2013 10 2013 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $80,680 $63,370 Not Implemented
OK0839 # 11 Y:2013 11 2013 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $32,511 $25,606 Implemented
OK0839 # 12 Y:2013 12 2013 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $4,901 $4,994 Not Implemented
OK0839 # 13 Y:2013 13 2013 OPTIMIZE PLANT POWER FACTOR $12,090 $11,638 Implemented
OK0839 # 14 Y:2013 14 2013 INSULATE BARE EQUIPMENT $1,275 $912 Not Implemented
OK0839 # 15 Y:2013 15 2013 INSULATE BARE EQUIPMENT $2,900 $4,158 Not Implemented
OK0839 # 16 Y:2013 16 2013 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $35,380 $0 Not Implemented
IA0492 # 01 Y:2013 01 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,544 $585 Implemented
IA0492 # 02 Y:2013 02 2013 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $4,344 $720 Implemented
IA0492 # 03 Y:2013 03 2013 INSTALL OCCUPANCY SENSORS $755 $1,617 Implemented