IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,043

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IA0492 # 04 Y:2013 04 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $914 $490 Not Implemented
IA0492 # 05 Y:2013 05 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,082 $105 Not Implemented
IA0492 # 06 Y:2013 06 2013 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,450 $590 Not Implemented
IA0492 # 07 Y:2013 07 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $230 $35 Not Implemented
LE0352 # 01 Y:2013 01 2013 INSTALL OCCUPANCY SENSORS $5,554 $7,670 Not Implemented
LE0352 # 02 Y:2013 02 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,145 $9,935 Not Implemented
LE0352 # 03 Y:2013 03 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $15,554 $4,768 Not Implemented
LE0352 # 04 Y:2013 04 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,631 $1,000 Not Implemented
LE0352 # 05 Y:2013 05 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,414 $2,750 Implemented
LE0352 # 06 Y:2013 06 2013 CLEAN CONDENSER TUBES $2,216 $12,000 Not Implemented
LE0352 # 07 Y:2013 07 2013 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,176 $1,000 Not Implemented
BS0012 # 01 Y:2013 01 2013 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,483 $900 Implemented
BS0012 # 02 Y:2013 02 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $3,601 $8,272 Implemented
BS0012 # 03 Y:2013 03 2013 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $5,998 $0 Implemented
BS0012 # 04 Y:2013 04 2013 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,065 $8,525 Not Implemented
BS0012 # 05 Y:2013 05 2013 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING $11,249 $3,500 Not Implemented
BS0012 # 06 Y:2013 06 2013 ELIMINATE/REDUCE AN OPERATION $1,098 $422 Not Implemented
BS0012 # 07 Y:2013 07 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,594 $26,100 Implemented
BS0012 # 08 Y:2013 08 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,596 $6,725 Not Implemented
BS0012 # 09 Y:2013 09 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $14,916 $14,075 Not Implemented
BS0012 # 10 Y:2013 10 2013 INSULATE BARE EQUIPMENT $340 $2,905 Not Implemented
UK1215 # 01 Y:2013 01 2013 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN $4,249 $2,200 Not Implemented
UK1215 # 02 Y:2013 02 2013 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,824 $4,516 Implemented
UK1215 # 03 Y:2013 03 2013 ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE $4,021 $1,610 Implemented
UK1215 # 04 Y:2013 04 2013 PAY UTILITY BILLS ON TIME $1,678 $0 Implemented