IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,777

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TN0476 # 01 Y:1992 01 1992 INSULATE BARE EQUIPMENT $9,523 $2,425 Not Implemented
TN0476 # 02 Y:1992 02 1992 REPAIR AND ELIMINATE STEAM LEAKS $8,013 $2,350 Not Implemented
TN0476 # 03 Y:1992 03 1992 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $56,030 $36,440 Not Implemented
TN0476 # 04 Y:1992 04 1992 INSTALL / REPAIR INSULATION ON STEAM LINES $4,854 $1,100 Not Implemented
TN0476 # 05 Y:1992 05 1992 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,303 $2,307 Not Implemented
TN0476 # 06 Y:1992 06 1992 IMPROVE LUBRICATION PRACTICES $3,357 $0 Not Implemented
UD0382 # 01 Y:1992 01 1992 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,352 $4,895 Implemented
UD0382 # 02 Y:1992 02 1992 INSTALL TIMERS AND/OR THERMOSTATS $177 $0 Not Implemented
UD0382 # 03 Y:1992 03 1992 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $542 $1,000 Not Implemented
UD0382 # 04 Y:1992 04 1992 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION $578 $0 Not Implemented
UD0383 # 01 Y:1992 01 1992 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $1,953 $500 Implemented
UD0383 # 02 Y:1992 02 1992 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION $8,673 $2,000 Implemented
UD0383 # 03 Y:1992 03 1992 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $11,174 $0 Not Implemented
UD0383 # 04 Y:1992 04 1992 RECOVER WASTE HEAT FROM EQUIPMENT $1,389 $400 Implemented
UD0383 # 05 Y:1992 05 1992 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,329 $13,345 Implemented
UD0383 # 06 Y:1992 06 1992 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $15,637 $47,000 Not Implemented
UD0384 # 01 Y:1992 01 1992 OPTIMIZE PLANT POWER FACTOR $31,568 $41,000 Not Implemented
UD0384 # 02 Y:1992 02 1992 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS $15,864 $22,000 Not Implemented
UD0384 # 03 Y:1992 03 1992 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $11,343 $3,000 Implemented
UD0384 # 04 Y:1992 04 1992 INSTALL TIMERS AND/OR THERMOSTATS $2,400 $800 Not Implemented
UD0384 # 05 Y:1992 05 1992 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,257 $23,650 Not Implemented
UD0385 # 01 Y:1992 01 1992 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $38,747 $60,000 Implemented
UD0385 # 02 Y:1992 02 1992 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS $6,576 $18,000 Not Implemented
UD0385 # 03 Y:1992 03 1992 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,703 $0 Implemented
UD0385 # 04 Y:1992 04 1992 RECOVER WASTE HEAT FROM EQUIPMENT $4,026 $3,294 Implemented