Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,520
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0138 # 03 Y:1999 | 03 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,541 | $2,100 | Not Implemented |
UM0138 # 04 Y:1999 | 04 | 1999 | RECOVER AND REUSE WASTE MATERIAL | $10,800 | $50,000 | Not Implemented |
UM0138 # 05 Y:1999 | 05 | 1999 | INSTALL EQUIPMENT TO MOVE PRODUCT | $5,127 | $0 | Implemented |
MA0435 # 01 Y:1999 | 01 | 1999 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $689 | $128 | Not Implemented |
MA0435 # 02 Y:1999 | 02 | 1999 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $281 | $328 | Not Implemented |
MA0435 # 03 Y:1999 | 03 | 1999 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $313 | $472 | Implemented |
MA0435 # 04 Y:1999 | 04 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $521 | $294 | Implemented |
MA0435 # 05 Y:1999 | 05 | 1999 | UPGRADE OBSOLETE EQUIPMENT | $1,957 | $350 | Not Implemented |
MA0435 # 06 Y:1999 | 06 | 1999 | INSTALL OCCUPANCY SENSORS | $590 | $248 | Implemented |
OK0571 # 01 Y:1999 | 01 | 1999 | USE OPTIMUM THICKNESS INSULATION | $3,598 | $649 | Implemented |
OK0571 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $615 | $130 | Not Implemented |
OK0571 # 03 Y:1999 | 03 | 1999 | INSTALL OCCUPANCY SENSORS | $7,735 | $1,689 | Implemented |
OK0571 # 04 Y:1999 | 04 | 1999 | INSTALL SET-BACK TIMERS | $372 | $387 | Not Implemented |
OK0571 # 05 Y:1999 | 05 | 1999 | PAY BILLS ON TIME TO AVOID LATE FEES | $782 | $0 | Implemented |
OK0571 # 06 Y:1999 | 06 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $5,160 | $10,828 | Implemented |
OK0571 # 07 Y:1999 | 07 | 1999 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $2,160 | $0 | Not Implemented |
ND0320 # 01 Y:1999 | 01 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $131 | $0 | Implemented |
ND0320 # 02 Y:1999 | 02 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $695 | $1,893 | Implemented |
ND0320 # 03 Y:1999 | 03 | 1999 | USE PHOTOCELL CONTROLS | $303 | $600 | Implemented |
ND0320 # 04 Y:1999 | 04 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $737 | $255 | Implemented |
ND0320 # 05 Y:1999 | 05 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $320 | $80 | Implemented |
ND0320 # 06 Y:1999 | 06 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $451 | $455 | Implemented |
ND0320 # 07 Y:1999 | 07 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $100 | $153 | Not Implemented |
ND0320 # 08 Y:1999 | 08 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,251 | $1,600 | Not Implemented |
ND0320 # 09 Y:1999 | 09 | 1999 | PURCHASE RE-CONDITIONED MATERIAL INSTEAD OF NEW | $969 | $1,376 | Not Implemented |