IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,055

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0325 # 05 Y:1995 05 1995 DIRECT WARMEST AIR TO COMBUSTION INTAKE $1,080 $570 Not Implemented
CO0325 # 06 Y:1995 06 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $690 $1,970 Not Implemented
CO0326 # 01 Y:1995 01 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $10,670 $23,310 Implemented
CO0326 # 02 Y:1995 02 1995 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $4,330 $6,500 Implemented
CO0326 # 03 Y:1995 03 1995 INSTALL / REPAIR INSULATION ON STEAM LINES $2,790 $1,040 Implemented
CO0326 # 04 Y:1995 04 1995 RECOVER WASTE HEAT FROM EQUIPMENT $2,460 $3,320 Not Implemented
CO0326 # 05 Y:1995 05 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,230 $530 Implemented
CO0326 # 06 Y:1995 06 1995 REPAIR AND ELIMINATE STEAM LEAKS $460 $160 Implemented
DS0020 # 01 Y:1995 01 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $10,077 $21,586 Not Implemented
DS0020 # 02 Y:1995 02 1995 INSTALL OCCUPANCY SENSORS $991 $2,006 Not Implemented
DS0020 # 03 Y:1995 03 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,483 $120 Implemented
DS0020 # 04 Y:1995 04 1995 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,134 $5,056 Not Implemented
OK0464 # 01 Y:1995 01 1995 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $37,301 $2,000 Implemented
OK0464 # 02 Y:1995 02 1995 USE PUMPS AND PIPING TO DECREASE THE FREQUENCY OF SPILLAGE DURING MATERIAL TRANSFER $3,872 $7,422 Implemented
OK0464 # 03 Y:1995 03 1995 DISTILL CONTAMINATED SOLVENTS FOR REUSE $6,347 $6,240 Not Implemented
OK0464 # 04 Y:1995 04 1995 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,609 $170 Implemented
OK0464 # 05 Y:1995 05 1995 INSTALL TIMERS AND/OR THERMOSTATS $4,193 $1,736 Implemented
OK0464 # 06 Y:1995 06 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $379 $300 Implemented
OK0464 # 07 Y:1995 07 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $267 $791 Implemented
OK0464 # 08 Y:1995 08 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $99 $240 Not Implemented
OK0458 # 01 Y:1995 01 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $616 $3,962 Not Implemented
OK0458 # 02 Y:1995 02 1995 INSTALL OCCUPANCY SENSORS $662 $760 Not Implemented
OK0458 # 03 Y:1995 03 1995 RECOVER WASTE HEAT FROM EQUIPMENT $633 $727 Not Implemented
OK0458 # 04 Y:1995 04 1995 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,010 $170 Not Implemented
OK0458 # 05 Y:1995 05 1995 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $60 $108 Not Implemented