Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,642
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0275 # 06 Y:1989 | 06 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,179 | $3,864 | Implemented |
KU0275 # 07 Y:1989 | 07 | 1989 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $204 | $0 | Implemented |
KU0275 # 08 Y:1989 | 08 | 1989 | IMPROVE LUBRICATION PRACTICES | $716 | $0 | Implemented |
KU0275 # 09 Y:1989 | 09 | 1989 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $349 | $358 | Implemented |
KU0275 # 10 Y:1989 | 10 | 1989 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $343 | $0 | Not Implemented |
KU0275 # 11 Y:1989 | 11 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $1,252 | $700 | Implemented |
KU0273 # 01 Y:1989 | 01 | 1989 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $25,620 | $38,400 | Implemented |
KU0273 # 02 Y:1989 | 02 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $10,343 | $1,400 | Implemented |
KU0273 # 03 Y:1989 | 03 | 1989 | INSTALL TURBULATORS | $5,599 | $5,760 | Implemented |
KU0273 # 04 Y:1989 | 04 | 1989 | KEEP BOILER TUBES CLEAN | $3,005 | $1,500 | Implemented |
KU0273 # 05 Y:1989 | 05 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,859 | $2,558 | Implemented |
KU0274 # 01 Y:1989 | 01 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,538 | $7,607 | Implemented |
KU0274 # 02 Y:1989 | 02 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $3,173 | $0 | Implemented |
KU0274 # 03 Y:1989 | 03 | 1989 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $362 | $300 | Implemented |
KU0274 # 04 Y:1989 | 04 | 1989 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $162 | $80 | Implemented |
KU0274 # 05 Y:1989 | 05 | 1989 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $700 | $3,700 | Not Implemented |
KU0274 # 06 Y:1989 | 06 | 1989 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $251 | $0 | Implemented |
KU0271 # 01 Y:1989 | 01 | 1989 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,720 | $6,000 | Not Implemented |
KU0271 # 02 Y:1989 | 02 | 1989 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $5,826 | $297 | Implemented |
KU0271 # 03 Y:1989 | 03 | 1989 | KEEP BOILER TUBES CLEAN | $5,300 | $1,500 | Implemented |
KU0271 # 04 Y:1989 | 04 | 1989 | INSULATE BARE EQUIPMENT | $3,940 | $900 | Not Implemented |
KU0271 # 05 Y:1989 | 05 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,327 | $6,000 | Not Implemented |
KU0271 # 06 Y:1989 | 06 | 1989 | USE RADIANT HEATER FOR SPOT HEATING | $3,371 | $6,000 | Not Implemented |
KU0271 # 07 Y:1989 | 07 | 1989 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,406 | $100 | Implemented |
KU0271 # 08 Y:1989 | 08 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,370 | $7,134 | Implemented |