Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,996
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0077 # 05 Y:1997 | 05 | 1997 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $9,768 | $11,000 | Not Implemented |
MS0077 # 06 Y:1997 | 06 | 1997 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $7,539 | $6,500 | Not Implemented |
MS0077 # 07 Y:1997 | 07 | 1997 | INSTALL AUTOMATIC PACKING EQUIPMENT | $17,000 | $1,113 | Not Implemented |
SD0164 # 01 Y:1997 | 01 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $50,256 | $53,800 | Implemented |
SD0164 # 02 Y:1997 | 02 | 1997 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $241,567 | $538,000 | Implemented |
SD0164 # 03 Y:1997 | 03 | 1997 | REPLACE BOILER | $204,328 | $78,000 | Not Implemented |
SD0164 # 04 Y:1997 | 04 | 1997 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $17,052 | $9,016 | Implemented |
SD0164 # 05 Y:1997 | 05 | 1997 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,242 | $1,500 | Implemented |
SD0164 # 06 Y:1997 | 06 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $704 | $0 | Implemented |
SD0164 # 07 Y:1997 | 07 | 1997 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $47,553 | $80,200 | Not Implemented |
SD0164 # 08 Y:1997 | 08 | 1997 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $13,700 | $15,000 | Not Implemented |
SD0164 # 09 Y:1997 | 09 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $11,250 | $0 | Implemented |
SD0164 # 10 Y:1997 | 10 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $10,000 | $0 | Implemented |
SD0164 # 11 Y:1997 | 11 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $6,000 | $0 | Implemented |
SD0164 # 12 Y:1997 | 12 | 1997 | CONVERT TO LESS TOXIC HYDROCARBON CLEANERS | $496 | $0 | Implemented |
SD0164 # 13 Y:1997 | 13 | 1997 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $164,025 | $20,000 | Implemented |
SD0164 # 14 Y:1997 | 14 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $29,160 | $1,000 | Implemented |
SD0164 # 15 Y:1997 | 15 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $36,450 | $8,000 | Implemented |
ME0208 # 01 Y:1997 | 01 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,030 | $600 | Implemented |
ME0208 # 02 Y:1997 | 02 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,766 | $20 | Implemented |
ME0208 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,949 | $3,274 | Not Implemented |
ME0208 # 04 Y:1997 | 04 | 1997 | PAY UTILITY BILLS ON TIME | $1,220 | $0 | Implemented |
ME0208 # 05 Y:1997 | 05 | 1997 | USE OPTIMUM THICKNESS INSULATION | $788 | $290 | Implemented |
ME0208 # 06 Y:1997 | 06 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $738 | $200 | Not Implemented |
ME0208 # 07 Y:1997 | 07 | 1997 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $452 | $0 | Implemented |