Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,713
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0292 # 06 Y:2002 | 06 | 2002 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $46,032 | $4,000 | Implemented |
UF0292 # 07 Y:2002 | 07 | 2002 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $468 | $0 | Implemented |
UF0292 # 08 Y:2002 | 08 | 2002 | INSTALL AUTOMATIC PART STORAGE / RETREVAL SYSTEM | $2,808 | $876 | Not Implemented |
UF0292 # 09 Y:2002 | 09 | 2002 | CROSS-TRAIN PERSONNEL TO AVOID LOST TIME | $11,250 | $24,938 | Implemented |
UF0292 # 10 Y:2002 | 10 | 2002 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $140,438 | $39,000 | Implemented |
UF0291 # 01 Y:2002 | 01 | 2002 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $1,755 | $1,050 | Implemented |
UF0291 # 02 Y:2002 | 02 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,427 | $192 | Not Implemented |
UF0291 # 03 Y:2002 | 03 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,917 | $6,752 | Implemented |
UF0291 # 04 Y:2002 | 04 | 2002 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $22,067 | $40,280 | Implemented |
UF0291 # 05 Y:2002 | 05 | 2002 | REPAIR AND ELIMINATE STEAM LEAKS | $1,124 | $450 | Implemented |
UF0291 # 06 Y:2002 | 06 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,424 | $490 | Implemented |
UF0291 # 07 Y:2002 | 07 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $15,235 | $25,190 | Implemented |
UF0291 # 08 Y:2002 | 08 | 2002 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $17,341 | $2,600 | Not Implemented |
UF0291 # 09 Y:2002 | 09 | 2002 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,394 | $20,000 | Not Implemented |
UF0291 # 10 Y:2002 | 10 | 2002 | SUBSTITUTE HOT PROCESS FLUIDS FOR STEAM | $16,158 | $0 | Not Implemented |
UF0291 # 11 Y:2002 | 11 | 2002 | MOVE BOILER TO MORE EFFICIENT LOCATION | $4,387 | $0 | Implemented |
UF0291 # 12 Y:2002 | 12 | 2002 | METER WASTE WATER | $4,133 | $1,500 | Implemented |
UF0291 # 13 Y:2002 | 13 | 2002 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $2,309 | $8,820 | Not Implemented |
UF0291 # 14 Y:2002 | 14 | 2002 | CROSS-TRAIN PERSONNEL TO AVOID LOST TIME | $12,120 | $16,900 | Not Implemented |
UF0289 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,791 | $2,728 | Implemented |
UF0289 # 02 Y:2001 | 02 | 2001 | INSTALL OCCUPANCY SENSORS | $2,566 | $1,457 | Not Implemented |
UF0289 # 03 Y:2001 | 03 | 2001 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $5,004 | $6,175 | Implemented |
UF0289 # 04 Y:2001 | 04 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $869 | $500 | Implemented |
UF0289 # 05 Y:2001 | 05 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,758 | $11,274 | Implemented |
UF0289 # 06 Y:2001 | 06 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $389 | $1,895 | Not Implemented |