IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,433

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IA0277 # 06 Y:2001 06 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,422 $40 Not Implemented
IA0277 # 07 Y:2001 07 2001 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $9,556 $0 Not Implemented
IA0277 # 08 Y:2001 08 2001 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $3,004 $5,000 Implemented
IA0277 # 09 Y:2001 09 2001 REPAIR AND ELIMINATE STEAM LEAKS $2,357 $2,400 Implemented
IA0277 # 10 Y:2001 10 2001 INSTALL EQUIPMENT TO MOVE PRODUCT $234,364 $136,500 n/a
IA0260 # 01 Y:2000 01 2000 INSTALL OCCUPANCY SENSORS $1,666 $1,530 Implemented
IA0260 # 02 Y:2000 02 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,392 $0 Implemented
IA0260 # 03 Y:2000 03 2000 INSTALL OCCUPANCY SENSORS $416 $985 Not Implemented
IA0260 # 04 Y:2000 04 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $722 $50 Implemented
IA0260 # 05 Y:2000 05 2000 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE $7,513 $14,000 Implemented
IA0260 # 06 Y:2000 06 2000 MINIMIZE WATER USAGE $243 $44 Implemented
IA0260 # 07 Y:2000 07 2000 INSTALL AUTOMATIC PACKING EQUIPMENT $41,184 $90,000 Implemented
KU0546 # 01 Y:2000 01 2000 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST $431,791 $2,400,000 Not Implemented
KU0546 # 02 Y:2000 02 2000 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $74,779 $244,140 Not Implemented
KU0546 # 03 Y:2000 03 2000 OPTIMIZE PLANT POWER FACTOR $17,000 $9,570 Not Implemented
KU0546 # 04 Y:2000 04 2000 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $2,500 $1,000 Implemented
KU0546 # 05 Y:2000 05 2000 RECOVER WASTE HEAT FROM EQUIPMENT $870 $740 Implemented
KU0543 # 01 Y:2000 01 2000 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $27,200 $0 Implemented
KU0543 # 02 Y:2000 02 2000 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $25,020 $50,000 Not Implemented
KU0543 # 03 Y:2000 03 2000 INSTALL OCCUPANCY SENSORS $430 $450 Not Implemented
KU0543 # 04 Y:2000 04 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $430 $50 Implemented
KU0543 # 05 Y:2000 05 2000 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $420 $100 Implemented
KU0543 # 06 Y:2000 06 2000 ELIMINATE A BY-PRODUCT $7,940 $9,680 Not Implemented
KU0543 # 07 Y:2000 07 2000 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $5,630 $8,000 Not Implemented
KU0543 # 08 Y:2000 08 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $56,920 $70,000 Not Implemented