Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,682
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0203 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,102 | $2,259 | Not Implemented |
WI0203 # 04 Y:1994 | 04 | 1994 | INSTALL OCCUPANCY SENSORS | $227 | $300 | Not Implemented |
WI0203 # 05 Y:1994 | 05 | 1994 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,743 | $2,844 | Implemented |
WI0203 # 06 Y:1994 | 06 | 1994 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $1,974 | $0 | Not Implemented |
WI0203 # 07 Y:1994 | 07 | 1994 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $422 | $0 | Not Implemented |
WI0203 # 08 Y:1994 | 08 | 1994 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,439 | $3,115 | Not Implemented |
WI0203 # 09 Y:1994 | 09 | 1994 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,175 | $1,700 | Implemented |
WI0203 # 10 Y:1994 | 10 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $590 | $200 | Not Implemented |
WI0203 # 11 Y:1994 | 11 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $286 | $0 | Not Implemented |
WI0203 # 12 Y:1994 | 12 | 1994 | REDUCE SCRAP PRODUCTION | $2,000 | $300 | Not Implemented |
WI0203 # 13 Y:1994 | 13 | 1994 | USE IN-PROCESS RECYCLING WHENEVER POSSIBLE | $2,500 | $500 | Not Implemented |
WI0202 # 01 Y:1994 | 01 | 1994 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $11,110 | $500 | Implemented |
WI0202 # 02 Y:1994 | 02 | 1994 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,157 | $4,594 | Not Implemented |
WI0202 # 03 Y:1994 | 03 | 1994 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,862 | $2,500 | Not Implemented |
WI0202 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,092 | $1,764 | Implemented |
WI0202 # 05 Y:1994 | 05 | 1994 | INSTALL OCCUPANCY SENSORS | $280 | $150 | Not Implemented |
WI0202 # 06 Y:1994 | 06 | 1994 | USE PHOTOCELL CONTROLS | $179 | $75 | Not Implemented |
WI0202 # 07 Y:1994 | 07 | 1994 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $833 | $0 | Not Implemented |
WI0202 # 08 Y:1994 | 08 | 1994 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $609 | $400 | Implemented |
WI0202 # 09 Y:1994 | 09 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $451 | $0 | Implemented |
WI0202 # 10 Y:1994 | 10 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $321 | $1,280 | Not Implemented |
BD0001 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,894 | $8,270 | Not Implemented |
BD0001 # 02 Y:1994 | 02 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,344 | $5,760 | Implemented |
BD0001 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,156 | $8,063 | Not Implemented |
BD0001 # 04 Y:1994 | 04 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $357 | $350 | Not Implemented |