IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,333

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0377 # 03 Y:2000 03 2000 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER $97,815 $113,670 Not Implemented
OR0377 # 04 Y:2000 04 2000 ELIMINATE PRACTICE OF MIXING WASTE STREAMS $108,000 $40,000 Implemented
OR0380 # 01 Y:2000 01 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $89,400 $280,000 Not Implemented
OR0380 # 02 Y:2000 02 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $15,389 $29,590 Not Implemented
OR0380 # 03 Y:2000 03 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $15,954 $30,046 Implemented
OR0380 # 04 Y:2000 04 2000 OPTIMIZE PLANT POWER FACTOR $4,853 $13,600 Implemented
OR0380 # 05 Y:2000 05 2000 USE PHOTOCELL CONTROLS $3,605 $605 Implemented
OR0380 # 06 Y:2000 06 2000 UPGRADE CONTROLS ON COMPRESSORS $647 $0 Implemented
OR0380 # 07 Y:2000 07 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,013 $0 Not Implemented
OR0380 # 08 Y:2000 08 2000 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $1,344 $7,500 Not Implemented
WV0205 # 01 Y:2000 01 2000 RECOVER WASTE HEAT FROM EQUIPMENT $11,419 $800 Not Implemented
WV0205 # 02 Y:2000 02 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,709 $800 Not Implemented
WV0205 # 03 Y:2000 03 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $347 $519 Implemented
WV0205 # 04 Y:2000 04 2000 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $7,568 $3,000 Implemented
WV0205 # 05 Y:2000 05 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $394 $50 Implemented
WV0205 # 06 Y:2000 06 2000 INSTALL SPECTRAL REFLECTORS / DELAMP $7,688 $7,933 Implemented
WV0205 # 07 Y:2000 07 2000 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $6,511 $600 Not Implemented
WV0205 # 08 Y:2000 08 2000 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $6,109 $1,500 Not Implemented
WV0205 # 09 Y:2000 09 2000 USE OPTIMUM THICKNESS INSULATION $171 $375 Implemented
WV0205 # 10 Y:2000 10 2000 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM $9,414 $1,000 Implemented
WV0205 # 11 Y:2000 11 2000 CONTRACT A WOOD PALLET RECYCLING COMPANY $480 $100 Implemented
WV0205 # 12 Y:2000 12 2000 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS $80 $0 Implemented
WV0205 # 13 Y:2000 13 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $5,182 $7,000 Not Implemented
WV0205 # 14 Y:2000 14 2000 INSTALL EQUIPMENT TO MOVE PRODUCT $77,688 $750 Not Implemented
WV0205 # 15 Y:2000 15 2000 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $35,000 $5,000 Not Implemented